Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 1998 |
Principal Product | Portland Cement |
NAICS | n/a |
SIC | 3241 - Cement, Hydraulic |
Sales | $50,000,000-$100,000,000 |
# of Employees | 134 |
Plant Area (Sq.Ft.) | 218,000 |
Annual Production | 1,300,000 Tons |
Production Hrs. Annual | 8,760 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $4,366,715 | 176,051,585 | kWh | $0.02 |
Electricity Demand | $1,906,197 | 29,306 | kW-months/year | $65.04 |
Electricity Fees | $5,934 | - | $ | - |
Natural Gas | $628,261 | 218,435 | MMBtu | $2.88 |
TOTAL ENERGY COSTS | $6,907,107 | |||
RECOMMENDED SAVINGS* | $3,847,053 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,539 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $1,364 Cost: $3,550 |
- | - | - | - | - | - | - | - | $1,364 | - |
- - kWh |
- - kW-months/year |
- - lb |
- - $ |
$1,364 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $2,950,000 Cost: $19,000,000 |
- | - | - | - | - | - | $2,950,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$2,950,000 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS |
Savings: $4,256 Cost: $7,500 |
$4,256 | 183,177 | - | - | - | - | - | - | - | - |
$4,256 183,177 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $7,919 Cost: $17,073 |
$6,163 | 265,240 | $1,756 | 27 | - | - | - | - | - | - |
$6,163 265,240 kWh |
$1,756 27 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $7,514 Cost: $2,827 |
$5,693 | 245,018 | $1,821 | 28 | - | - | - | - | - | - |
$5,693 245,018 kWh |
$1,821 28 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5216 RECYCLE NONFERROUS DUST |
Savings: $876,000 Cost: $900,000 |
- | - | - | - | $876,000 | 146,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
$876,000 146,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $3,847,053 Cost: $19,930,950 |
$16,112 | 693,435 | $3,577 | 55 | $876,000 | 146,000 | $2,950,000 | - | $1,364 | - | $16,112 693,435 kWh |
$3,577 55 kW-months/year |
$876,000 146,000 lb |
$2,950,000 - $ |
$1,364 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,539 Cost: $28,123 |
$10,419 | 448,417 | $1,756 | 27 | - | - | - | - | $1,364 | - | $10,419 448,417 kWh |
$1,756 27 kW-months/year |
- - lb |
- - $ |
$1,364 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost |