Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri, Rolla |
---|---|
Assessment Year | 1999 |
Principal Product | Truck Engine Oil Coolers |
NAICS | n/a |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $10,000,000-$50,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 128,420 |
Annual Production | 114,000 Units |
Production Hrs. Annual | 6,000 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $196,186 | 5,342,907 | kWh | $0.04 |
Electricity Demand | $82,944 | 1,812 | kW-months/year | $45.77 |
Electricity Fees | $31,179 | - | $ | - |
Natural Gas | $45,779 | 12,795 | MMBtu | $3.58 |
TOTAL ENERGY COSTS | $372,501 | |||
RECOMMENDED SAVINGS* | $90,605 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $67,488 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $4,918 Cost: $100 |
$4,172 | 98,183 | $746 | 16 | - | - | - | - | - | - | - | - |
$4,172 98,183 kWh |
$746 16 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1113 REDUCE COMBUSTION AIR FLOW TO OPTIMUM |
Savings: $417 Cost: $500 |
- | - | - | - | $417 | 116 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$417 116 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $5,100 Cost: - |
- | - | - | - | - | - | $5,100 | 3,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$5,100 3,000 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $57,053 Cost: - |
- | - | - | - | - | - | - | - | - | - | $57,053 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$57,053 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $23,117 Cost: $30,000 |
- | - | - | - | - | - | - | - | $23,117 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$23,117 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $90,605 Cost: $30,600 |
$4,172 | 98,183 | $746 | 16 | $417 | 116 | $5,100 | 3,000 | $23,117 | - | $57,053 | - | $4,172 98,183 kWh |
$746 16 kW-months/year |
$417 116 MMBtu |
$5,100 3,000 lb |
$23,117 - $ |
$57,053 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $67,488 Cost: $600 |
$4,172 | 98,183 | $746 | 16 | $417 | 116 | $5,100 | 3,000 | - | - | $57,053 | - | $4,172 98,183 kWh |
$746 16 kW-months/year |
$417 116 MMBtu |
$5,100 3,000 lb |
- - $ |
$57,053 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes |