Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 1994 |
Principal Product | Furniture |
NAICS | n/a |
SIC | 2512 - Upholstered Household Furniture |
Sales | $10,000,000-$50,000,000 |
# of Employees | 387 |
Plant Area (Sq.Ft.) | 265,000 |
Annual Production | 109,472 Pieces |
Production Hrs. Annual | 2,250 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $101,803 | 1,796,307 | kWh | $0.06 |
Natural Gas | $24,437 | 3,913 | MMBtu | $6.25 |
TOTAL ENERGY COSTS | $126,240 | |||
RECOMMENDED SAVINGS* | $13,010 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $5,137 Cost: $2,700 |
$5,137 | 171,161 | - | - |
$5,137 171,161 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7227 USE WATER ON AIR CONDITIONING EXCHANGER TO IMPROVE HEAT TRANSFER AND INCREASE AIR CONDITIONER EFFICIENCY |
Savings: $1,737 Cost: $8,100 |
$1,737 | 58,030 | - | - |
$1,737 58,030 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2711 UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING |
Savings: $628 Cost: $500 |
- | - | $628 | 101 |
- - kWh |
$628 101 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,714 Cost: $1,321 |
$3,714 | 42,790 | - | - |
$3,714 42,790 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,794 Cost: $1,000 |
- | - | $1,794 | 289 |
- - kWh |
$1,794 289 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,010 Cost: $13,621 |
$10,588 | 271,981 | $2,422 | 390 | $10,588 271,981 kWh |
$2,422 390 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |