Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 1996 |
Principal Product | File Folders, Computer Paper, and Paper Pads |
NAICS | n/a |
SIC | 2652 - Setup Paperboard Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 156 |
Plant Area (Sq.Ft.) | 294,000 |
Annual Production | 26,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $215,464 | 5,021,395 | kWh | $0.04 |
Electricity Demand | $37,683 | 11,008 | kW-months/year | $3.42 |
Electricity Fees | $80,360 | - | $ | - |
Natural Gas | $59,392 | 12,857 | MMBtu | $4.62 |
TOTAL ENERGY COSTS | $195,079 | |||
RECOMMENDED SAVINGS* | $53,153 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $44,638 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Primary Raw Material | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $5,086 Cost: $3,378 |
- | - | - | - | - | - | $5,086 | 1,019 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$5,086 1,019 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $3,429 Cost: $402 |
$2,898 | 65,944 | - | - | $531 | - | - | - | - | - | - | - |
$2,898 65,944 kWh |
- - kW-months/year |
$531 - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6214 SHUT OFF PILOTS IN STANDBY EQUIPMENT |
Savings: $2,600 Cost: $120 |
- | - | - | - | - | - | $2,600 | 521 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$2,600 521 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7122 DISCONNECT BALLASTS |
Savings: $2,838 Cost: $40 |
$2,097 | 47,773 | $238 | 95 | $503 | - | - | - | - | - | - | - |
$2,097 47,773 kWh |
$238 95 kW-months/year |
$503 - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $39,200 Cost: $2,000 |
- | - | - | - | - | - | - | - | $(-5,600) | 112,000 | $44,800 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$(-5,600) 112,000 lb |
$44,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $53,153 Cost: $5,940 |
$4,995 | 113,717 | $238 | 95 | $1,034 | - | $7,686 | 1,540 | $(-5,600) | 112,000 | $44,800 | - | $4,995 113,717 kWh |
$238 95 kW-months/year |
$1,034 - $ |
$7,686 1,540 MMBtu |
$(-5,600) 112,000 lb |
$44,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $44,638 Cost: $2,160 |
$2,097 | 47,773 | $238 | 95 | $503 | - | $2,600 | 521 | $(-5,600) | 112,000 | $44,800 | - | $2,097 47,773 kWh |
$238 95 kW-months/year |
$503 - $ |
$2,600 521 MMBtu |
$(-5,600) 112,000 lb |
$44,800 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Primary Raw Material | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Primary Raw Material |