Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 1996 |
Principal Product | Clothing |
NAICS | n/a |
SIC | 2326 - Men's and Boys' Work Clothing |
Sales | $50,000,000-$100,000,000 |
# of Employees | 80 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 21,888,000 Pieces |
Production Hrs. Annual | 3,840 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $129,205 | 4,165,299 | kWh | $0.03 |
Electricity Demand | $102,690 | 11,709 | kW-months/year | $8.77 |
Electricity Fees | $3,582 | - | $ | - |
Natural Gas | $17,898 | 6,156 | MMBtu | $2.91 |
TOTAL ENERGY COSTS | $290,259 | |||
RECOMMENDED SAVINGS* | $56,507 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $19,052 Cost: $47,376 |
$9,128 | 294,256 | $9,924 | 1,021 | - | - | - | - |
$9,128 294,256 kWh |
$9,924 1,021 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $972 Cost: $180 |
$330 | 10,551 | $642 | 66 | - | - | - | - |
$330 10,551 kWh |
$642 66 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7314 REDUCE VENTILATION AIR |
Savings: $3,442 Cost: $3,975 |
$750 | 24,033 | $2,692 | 277 | - | - | - | - |
$750 24,033 kWh |
$2,692 277 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $1,192 Cost: $750 |
- | - | $1,192 | - | - | - | - | - |
- - kWh |
$1,192 - kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,017 Cost: $2,926 |
- | - | - | - | $1,017 | 350 | - | - |
- - kWh |
- - kW-months/year |
$1,017 350 MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $4,751 Cost: $13,574 |
- | - | - | - | $4,751 | 1,633 | - | - |
- - kWh |
- - kW-months/year |
$4,751 1,633 MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $3,597 Cost: $8,560 |
$3,597 | 116,061 | - | - | - | - | - | - |
$3,597 116,061 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $9,720 Cost: - |
- | - | - | - | - | - | $9,720 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$9,720 - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $12,764 Cost: $15,100 |
- | - | - | - | - | - | $12,764 | 184,000 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$12,764 184,000 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $56,507 Cost: $92,441 |
$13,805 | 444,901 | $14,450 | 1,364 | $5,768 | 1,983 | $22,484 | 184,000 | $13,805 444,901 kWh |
$14,450 1,364 kW-months/year |
$5,768 1,983 MMBtu |
$22,484 184,000 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) |