Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 1997 |
Principal Product | Conveyor Systems |
NAICS | n/a |
SIC | 3535 - Conveyors And Conveying Equipment |
Sales | $50,000,000-$100,000,000 |
# of Employees | 380 |
Plant Area (Sq.Ft.) | 304,000 |
Annual Production | 35,000,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $243,110 | 7,837,339 | kWh | $0.03 |
Electricity Demand | $160,954 | 17,794 | kW-months/year | $9.05 |
Electricity Fees | $6,165 | - | $ | - |
Natural Gas | $142,844 | 48,497 | MMBtu | $2.95 |
TOTAL ENERGY COSTS | $265,730 | |||
RECOMMENDED SAVINGS* | $136,155 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $32,037 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $4,514 Cost: $4,620 |
$4,514 | 145,662 | - | - | - | - | - | - | - | - | - | - | - | - |
$4,514 145,662 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $16,653 Cost: $30,962 |
$9,869 | 317,995 | $6,784 | 698 | - | - | - | - | - | - | - | - | - | - |
$9,869 317,995 kWh |
$6,784 698 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,556 Cost: $616 |
$1,556 | 50,117 | - | - | - | - | - | - | - | - | - | - | - | - |
$1,556 50,117 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,390 Cost: $541 |
$962 | 31,067 | $428 | 44 | - | - | - | - | - | - | - | - | - | - |
$962 31,067 kWh |
$428 44 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2443 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR |
Savings: $9,480 Cost: $955 |
- | - | - | - | $9,480 | 3,214 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$9,480 3,214 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $8,888 Cost: - |
- | - | - | - | - | - | - | - | $8,888 | 551,250 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$8,888 551,250 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8141 REGENERATE CLEANING SOLVENT ON-SITE AND REUSE |
Savings: $12,074 Cost: $13,000 |
- | - | - | - | - | - | $2,189 | 651 | - | - | - | - | $9,885 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,189 651 gal |
- - lb |
- - $ |
$9,885 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.452 ELIMINATE SHIFT |
Savings: $81,600 Cost: - |
- | - | - | - | - | - | - | - | - | - | $81,600 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$81,600 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $136,155 Cost: $50,694 |
$16,901 | 544,841 | $7,212 | 742 | $9,480 | 3,214 | $2,189 | 651 | $8,888 | 551,250 | $81,600 | - | $9,885 | - | $16,901 544,841 kWh |
$7,212 742 kW-months/year |
$9,480 3,214 MMBtu |
$2,189 651 gal |
$8,888 551,250 lb |
$81,600 - $ |
$9,885 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $32,037 Cost: $37,078 |
$15,345 | 494,724 | $7,212 | 742 | $9,480 | 3,214 | - | - | - | - | - | - | - | - | $15,345 494,724 kWh |
$7,212 742 kW-months/year |
$9,480 3,214 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |