Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 1998 |
Principal Product | Beverages |
NAICS | n/a |
SIC | 2086 - Bottled And Canned Soft Drinks |
Sales | $10,000,000-$50,000,000 |
# of Employees | 48 |
Plant Area (Sq.Ft.) | 86,700 |
Annual Production | 2,200,000 Pieces |
Production Hrs. Annual | 4,400 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $72,182 | 1,686,694 | kWh | $0.04 |
Electricity Demand | $47,216 | 6,557 | kW-months/year | $7.20 |
Electricity Fees | $3,188 | - | $ | - |
Natural Gas | $32,552 | 6,208 | MMBtu | $5.24 |
TOTAL ENERGY COSTS | $166,742 | |||
RECOMMENDED SAVINGS* | $91,714 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $23,520 Cost: $9,000 |
- | - | - | - | $23,520 | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$23,520 - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,198 Cost: $8,073 |
$1,013 | 30,481 | $1,153 | 113 | $32 | - | - | - | - | - | - | - | - | - |
$1,013 30,481 kWh |
$1,153 113 kW-months/year |
$32 - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,589 Cost: $2,068 |
- | - | - | - | - | - | $3,589 | 700 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$3,589 700 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $149 Cost: $103 |
$80 | 2,345 | $67 | 7 | $2 | - | - | - | - | - | - | - | - | - |
$80 2,345 kWh |
$67 7 kW-months/year |
$2 - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2447 HEAT WATER WITH EXHAUST HEAT |
Savings: $3,658 Cost: $10,841 |
- | - | - | - | - | - | $3,658 | 713 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$3,658 713 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $525 Cost: $1,160 |
$517 | 15,533 | - | - | $8 | - | - | - | - | - | - | - | - | - |
$517 15,533 kWh |
- - kW-months/year |
$8 - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $109 Cost: $27 |
- | - | - | - | $109 | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$109 - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $18,800 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $18,800 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
$18,800 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $3,485 Cost: $50 |
- | - | - | - | - | - | - | - | - | - | $3,485 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
$3,485 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.522 MODIFY STORAGE SPACE TO AVOID RENTAL OF A WAREHOUSE |
Savings: $35,681 Cost: $63,600 |
- | - | - | - | - | - | - | - | $3,699 | - | $27,822 | - | $4,160 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$3,699 - $ |
$27,822 - $ |
$4,160 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $91,714 Cost: $94,922 |
$1,610 | 48,359 | $1,220 | 120 | $23,671 | - | $7,247 | 1,413 | $3,699 | - | $31,307 | - | $22,960 | - | $1,610 48,359 kWh |
$1,220 120 kW-months/year |
$23,671 - $ |
$7,247 1,413 MMBtu |
$3,699 - $ |
$31,307 - $ |
$22,960 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost |