IAC Assessment: MS0156
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MS0156
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Mississippi State
Assessment Year 2000
Principal Product Residential A-Coil Evaporators
NAICS n/a
SIC 3585 - Refrigeration And Heating Equipment
Sales $50,000,000-$100,000,000
# of Employees 525
Plant Area (Sq.Ft.) 350,000
Annual Production 808,000 Pieces
Production Hrs. Annual 6,520
Location (State) MS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $367,567 10,919,988 kWh $0.03
Electricity Demand $219,432 26,030 kW-months/year $8.43
Electricity Fees $(-5,811) - $ -
Natural Gas $46,031 15,234 MMBtu $3.02
TOTAL ENERGY COSTS $713,876
RECOMMENDED SAVINGS* $118,720 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $79,890
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Water Disposal Water Consumption Electricity Usage Electricity Demand Electricity Fees Water Disposal Water Consumption
$ kWh $ kW-months/year $ $ $ Tgal $ Tgal
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$31,264
Cost:
$583
$20,015 594,666 $10,787 1,094 $462 - - - - - $20,015
594,666
kWh
$10,787
1,094
kW-months/year
$462
-
$
-
-
Tgal
-
-
Tgal
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$5,681
Cost:
$200
$5,597 166,178 - - $84 - - - - - $5,597
166,178
kWh
-
-
kW-months/year
$84
-
$
-
-
Tgal
-
-
Tgal
03: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS Savings:
$7,566
Cost:
-
- - $7,454 756 $112 - - - - - -
-
kWh
$7,454
756
kW-months/year
$112
-
$
-
-
Tgal
-
-
Tgal
04: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$74,209
Cost:
$6,000
- - - - - - $23,960 19,584,000 $50,249 - -
-
kWh
-
-
kW-months/year
-
-
$
$23,960
19,584,000
Tgal
$50,249
-
Tgal
TOTAL RECOMMENDED Savings:
$118,720
Cost:
$6,783
$25,612 760,844 $18,241 1,850 $658 - $23,960 19,584,000 $50,249 - $25,612
760,844
kWh
$18,241
1,850
kW-months/year
$658
-
$
$23,960
19,584,000
Tgal
$50,249
-
Tgal
TOTAL IMPLEMENTED Savings:
$79,890
Cost:
$6,200
$5,597 166,178 - - $84 - $23,960 19,584,000 $50,249 - $5,597
166,178
kWh
-
-
kW-months/year
$84
-
$
$23,960
19,584,000
Tgal
$50,249
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ $ $ Tgal $ Tgal
Electricity Usage Electricity Demand Electricity Fees Water Disposal Water Consumption Electricity Usage Electricity Demand Electricity Fees Water Disposal Water Consumption