Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2002 |
Principal Product | Industrial handling equipment |
NAICS | n/a |
SIC | 3599 - Industrial Machinery, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 62 |
Plant Area (Sq.Ft.) | 68,000 |
Annual Production | 4,000 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $34,364 | 808,560 | kWh | $0.04 |
Electricity Demand | $21,196 | 3,533 | kW-months/year | $6.00 |
Electricity Fees | $7,366 | - | $ | - |
Natural Gas | $5,246 | 398 | MMBtu | $13.18 |
TOTAL ENERGY COSTS | $73,751 | |||
RECOMMENDED SAVINGS* | $5,696 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,204 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,668 Cost: $2,700 |
- | - | $2,668 | - | - | - |
- - kWh |
$2,668 - $ |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $919 Cost: $591 |
$906 | 21,216 | $13 | - | - | - |
$906 21,216 kWh |
$13 - $ |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $244 Cost: $129 |
$240 | 5,644 | $4 | - | - | - |
$240 5,644 kWh |
$4 - $ |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $960 Cost: - |
- | - | - | - | $960 | 60,000 |
- - kWh |
- - $ |
$960 60,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $905 Cost: $374 |
- | - | - | - | $905 | 2,016 |
- - kWh |
- - $ |
$905 2,016 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $5,696 Cost: $3,794 |
$1,146 | 26,860 | $2,685 | - | $1,865 | 62,016 | $1,146 26,860 kWh |
$2,685 - $ |
$1,865 62,016 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,204 Cost: $129 |
$240 | 5,644 | $4 | - | $960 | 60,000 | $240 5,644 kWh |
$4 - $ |
$960 60,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Electricity Usage | Electricity Fees | Solid Waste (non-haz) |