Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2003 |
Principal Product | Metal Castings and Fabricated Equipment |
NAICS | 332312 - Fabricated Structural Metal Manufacturing |
SIC | 3441 - Fabricated Structural Metal |
Sales | $10,000,000-$50,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 400,000 |
Annual Production | 3,000,000 Pounds |
Production Hrs. Annual | 4,500 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $192,183 | 4,632,272 | kWh | $0.04 |
Electricity Fees | $119,284 | - | $ | - |
Natural Gas | $25,538 | 3,056 | MMBtu | $8.36 |
TOTAL ENERGY COSTS | $342,704 | |||
RECOMMENDED SAVINGS* | $11,106 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,844 Cost: $4,555 |
$614 | 34,966 | $367 | 48 | $863 | - | - | - |
$614 34,966 kWh |
$367 48 kW-months/year |
$863 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,701 Cost: $480 |
$855 | 34,392 | - | - | $846 | - | - | - |
$855 34,392 kWh |
- - kW-months/year |
$846 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,654 Cost: $3,151 |
$463 | 26,390 | $535 | 70 | $656 | - | - | - |
$463 26,390 kWh |
$535 70 kW-months/year |
$656 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $1,634 Cost: $50 |
- | - | - | - | $1,634 | - | - | - |
- - kWh |
- - kW-months/year |
$1,634 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,595 Cost: $3,236 |
$996 | 24,092 | - | 72 | $599 | - | - | - |
$996 24,092 kWh |
- 72 kW-months/year |
$599 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,207 Cost: $500 |
$503 | 26,170 | - | - | $704 | - | - | - |
$503 26,170 kWh |
- - kW-months/year |
$704 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7141 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS |
Savings: $485 Cost: $568 |
$115 | 6,465 | $184 | 39 | $186 | - | - | - |
$115 6,465 kWh |
$184 39 kW-months/year |
$186 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6214 SHUT OFF PILOTS IN STANDBY EQUIPMENT |
Savings: $424 Cost: $64 |
- | - | - | - | - | - | $424 | 54 |
- - kWh |
- - kW-months/year |
- - $ |
$424 54 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $390 Cost: $25 |
- | - | - | - | - | - | $390 | - |
- - kWh |
- - kW-months/year |
- - $ |
$390 - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $172 Cost: $38 |
$72 | 4,081 | - | - | $100 | - | - | - |
$72 4,081 kWh |
- - kW-months/year |
$100 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,106 Cost: $12,667 |
$3,618 | 156,556 | $1,086 | 229 | $5,588 | - | $814 | 54 | $3,618 156,556 kWh |
$1,086 229 kW-months/year |
$5,588 - $ |
$814 54 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |