Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2004 |
Principal Product | coaxial cable |
NAICS | 331318 - Other Aluminum Rolling, Drawing, and Extruding |
SIC | 3357 - Nonferrous Wiredrawing & Insulating |
Sales | $10,000,000-$50,000,000 |
# of Employees | 77 |
Plant Area (Sq.Ft.) | 218,785 |
Annual Production | 88,370,000 Thousand Feet |
Production Hrs. Annual | 5,400 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $287,529 | 6,610,018 | kWh | $0.04 |
Electricity Demand | $64,013 | 19,854 | kW-months/year | $3.22 |
Electricity Fees | $82,960 | - | $ | - |
Natural Gas | $51,981 | 5,349 | MMBtu | $9.72 |
TOTAL ENERGY COSTS | $486,483 | |||
RECOMMENDED SAVINGS* | $26,531 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $11,681 Cost: $14,325 |
- | - | - | - | - | - | $11,681 | 1,202 |
- - kWh |
- - kW-months/year |
- - $ |
$11,681 1,202 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $4,013 Cost: $5,320 |
$3,039 | 70,952 | - | - | $974 | - | - | - |
$3,039 70,952 kWh |
- - kW-months/year |
$974 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $2,671 Cost: $25 |
- | - | - | - | - | - | $2,671 | - |
- - kWh |
- - kW-months/year |
- - $ |
$2,671 - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.6124 BURN WASTE OIL FOR HEAT |
Savings: $2,499 Cost: $1,974 |
- | - | - | - | - | - | $2,499 | 272 |
- - kWh |
- - kW-months/year |
- - $ |
$2,499 272 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,874 Cost: $1,218 |
- | - | - | - | - | - | $1,874 | 193 |
- - kWh |
- - kW-months/year |
- - $ |
$1,874 193 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,736 Cost: $158 |
$1,315 | 30,696 | - | - | $421 | - | - | - |
$1,315 30,696 kWh |
- - kW-months/year |
$421 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,050 Cost: $1,558 |
$795 | 18,558 | - | - | $255 | - | - | - |
$795 18,558 kWh |
- - kW-months/year |
$255 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $668 Cost: $178 |
$427 | 9,959 | $86 | 27 | $155 | - | - | - |
$427 9,959 kWh |
$86 27 kW-months/year |
$155 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7122 DISCONNECT BALLASTS |
Savings: $339 Cost: $564 |
$222 | 5,178 | $38 | 12 | $79 | - | - | - |
$222 5,178 kWh |
$38 12 kW-months/year |
$79 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $26,531 Cost: $25,320 |
$5,798 | 135,343 | $124 | 39 | $1,884 | - | $18,725 | 1,667 | $5,798 135,343 kWh |
$124 39 kW-months/year |
$1,884 - $ |
$18,725 1,667 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |