IAC Assessment: MS0265
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MS0265
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Mississippi State
Assessment Year 2004
Principal Product Wire Cloth
NAICS 332618 - Other Fabricated Wire Product Manufacturing
SIC 3496 - Misc. Fabricated Wire Products
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 165,000
Annual Production 1,000 Thousand Feet
Production Hrs. Annual 8,400
Location (State) MS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $195,007 4,376,577 kWh $0.04
Electricity Demand $36,203 10,295 kW-months/year $3.52
Electricity Fees $81,873 - $ -
Natural Gas $26,476 2,818 MMBtu $9.40
TOTAL ENERGY COSTS $339,559
RECOMMENDED SAVINGS* $59,385 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $38,455
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (non-haz) Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (non-haz)
$ kWh $ kW-months/year $ $ $ MMBtu $ gal
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$36,775
Cost:
$59,467
$18,681 560,519 $2,804 801 $15,290 - - - - - $18,681
560,519
kWh
$2,804
801
kW-months/year
$15,290
-
$
-
-
MMBtu
-
-
gal
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$10,523
Cost:
$32,157
$5,341 160,261 $809 231 $4,373 - - - - - $5,341
160,261
kWh
$809
231
kW-months/year
$4,373
-
$
-
-
MMBtu
-
-
gal
03: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$5,480
Cost:
$2,430
$3,069 92,084 - - $2,411 - - - - - $3,069
92,084
kWh
-
-
kW-months/year
$2,411
-
$
-
-
MMBtu
-
-
gal
04: 3.6124 BURN WASTE OIL FOR HEAT Savings:
$3,362
Cost:
$3,129
- - - - - - $1,362 123 $2,000 1,100 -
-
kWh
-
-
kW-months/year
-
-
$
$1,362
123
MMBtu
$2,000
1,100
gal
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,680
Cost:
$189
$941 28,245 - - $739 - - - - - $941
28,245
kWh
-
-
kW-months/year
$739
-
$
-
-
MMBtu
-
-
gal
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$791
Cost:
$472
$443 13,291 - - $348 - - - - - $443
13,291
kWh
-
-
kW-months/year
$348
-
$
-
-
MMBtu
-
-
gal
07: 2.6214 SHUT OFF PILOTS IN STANDBY EQUIPMENT Savings:
$774
Cost:
$176
- - - - - - $774 82 - - -
-
kWh
-
-
kW-months/year
-
-
$
$774
82
MMBtu
-
-
gal
TOTAL RECOMMENDED Savings:
$59,385
Cost:
$98,020
$28,475 854,400 $3,613 1,032 $23,161 - $2,136 205 $2,000 1,100 $28,475
854,400
kWh
$3,613
1,032
kW-months/year
$23,161
-
$
$2,136
205
MMBtu
$2,000
1,100
gal
TOTAL IMPLEMENTED Savings:
$38,455
Cost:
$59,656
$19,622 588,764 $2,804 801 $16,029 - - - - - $19,622
588,764
kWh
$2,804
801
kW-months/year
$16,029
-
$
-
-
MMBtu
-
-
gal
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ gal
Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (non-haz) Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (non-haz)