Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2008 |
Principal Product | Pharmaceuticals |
NAICS | 325412 - Pharmaceutical Preparation Manufacturing |
SIC | 2834 - Pharmaceutical Preparations |
Sales | $100,000,000-$500,000,000 |
# of Employees | 375 |
Plant Area (Sq.Ft.) | 225,000 |
Annual Production | 900,000,000 Units |
Production Hrs. Annual | 8,736 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,171,865 | 19,067,233 | kWh | $0.06 |
Electricity Demand | $400,152 | 32,151 | kW-months/year | $12.45 |
Natural Gas | $902,110 | 89,346 | MMBtu | $10.10 |
TOTAL ENERGY COSTS | $2,474,127 | |||
RECOMMENDED SAVINGS* | $140,143 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $56,229 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $38,137 Cost: $280 |
- | - | - | - | - | - | $38,137 | 3,586 |
- - kWh |
- - kW-months/year |
- - $ |
$38,137 3,586 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $24,959 Cost: $7,500 |
- | - | - | - | - | - | $24,959 | 2,347 |
- - kWh |
- - kW-months/year |
- - $ |
$24,959 2,347 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $43,147 Cost: $30,570 |
$31,111 | 596,913 | $11,398 | 820 | $638 | - | - | - |
$31,111 596,913 kWh |
$11,398 820 kW-months/year |
$638 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $17,965 Cost: $34,830 |
$17,699 | 339,595 | - | - | $266 | - | - | - |
$17,699 339,595 kWh |
- - kW-months/year |
$266 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,037 Cost: $389 |
$6,932 | 133,029 | - | - | $105 | - | - | - |
$6,932 133,029 kWh |
- - kW-months/year |
$105 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,045 Cost: $8,725 |
$4,357 | 83,596 | $1,599 | 115 | $89 | - | - | - |
$4,357 83,596 kWh |
$1,599 115 kW-months/year |
$89 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,338 Cost: $13,840 |
$1,318 | 25,290 | - | - | $20 | - | - | - |
$1,318 25,290 kWh |
- - kW-months/year |
$20 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,515 Cost: $476 |
$927 | 17,792 | $566 | 41 | $22 | - | - | - |
$927 17,792 kWh |
$566 41 kW-months/year |
$22 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $140,143 Cost: $96,610 |
$62,344 | 1,196,215 | $13,563 | 976 | $1,140 | - | $63,096 | 5,933 | $62,344 1,196,215 kWh |
$13,563 976 kW-months/year |
$1,140 - $ |
$63,096 5,933 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $56,229 Cost: $39,684 |
$42,400 | 813,538 | $12,997 | 935 | $832 | - | - | - | $42,400 813,538 kWh |
$12,997 935 kW-months/year |
$832 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |