Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2009 |
Principal Product | Front End Modules |
NAICS | 336111 - Automobile Manufacturing |
SIC | 3711 - Motor Vehicles And Car Bodies |
Sales | $100,000,000-$500,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 88,000 |
Annual Production | 160,000 Pieces |
Production Hrs. Annual | 4,608 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $91,974 | 1,835,880 | kWh | $0.05 |
Electricity Demand | $18,446 | 3,288 | kW-months/year | $5.61 |
Electricity Fees | $1,654 | - | $ | - |
Natural Gas | $22,213 | 2,076 | MMBtu | $10.70 |
TOTAL ENERGY COSTS | $134,287 | |||
RECOMMENDED SAVINGS* | $17,985 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,919 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $14,689 Cost: $21,753 |
$11,202 | 224,032 | $3,271 | 583 | $216 | - |
$11,202 224,032 kWh |
$3,271 583 kW-months/year |
$216 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,230 Cost: $391 |
$3,183 | 62,718 | - | - | $47 | - |
$3,183 62,718 kWh |
- - kW-months/year |
$47 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $66 Cost: $510 |
$57 | 1,139 | $8 | 2 | $1 | - |
$57 1,139 kWh |
$8 2 kW-months/year |
$1 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $17,985 Cost: $22,654 |
$14,442 | 287,889 | $3,279 | 585 | $264 | - | $14,442 287,889 kWh |
$3,279 585 kW-months/year |
$264 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,919 Cost: $22,144 |
$14,385 | 286,750 | $3,271 | 583 | $263 | - | $14,385 286,750 kWh |
$3,271 583 kW-months/year |
$263 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees |