Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Michigan State University |
---|---|
Assessment Year | 2022 |
Principal Product | Tooling products and manufacturing equipment |
NAICS | 333519 - Rolling Mill and Other Metalworking Machinery Manufacturing |
SIC | 3569 - General Industrial Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 69,930 |
Annual Production | 8,000 Pieces |
Production Hrs. Annual | 2,600 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $79,205 | 552,180 | kWh | $0.14 |
Electricity Fees | $9,015 | - | $ | - |
Natural Gas | $11,241 | 1,383 | MMBtu | $8.13 |
TOTAL ENERGY COSTS | $99,461 | |||
RECOMMENDED SAVINGS* | $13,790 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,438 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Personnel Changes | Electricity Usage | Electricity Fees | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $6,907 Cost: $21,510 |
$907 | 6,479 | - | - | $6,000 | - |
$907 6,479 kWh |
- - $ |
$6,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.1161 ELIMINATE/REDUCE AN OPERATION |
Savings: $588 Cost: - |
$588 | 4,200 | - | - | - | - |
$588 4,200 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $226 Cost: $200 |
$226 | 1,615 | - | - | - | - |
$226 1,615 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $2,126 Cost: $1,367 |
- | - | $2,126 | - | - | - |
- - kWh |
$2,126 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $3,420 Cost: $1,933 |
$3,420 | 24,427 | - | - | - | - |
$3,420 24,427 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $85 Cost: $80 |
$85 | 605 | - | - | - | - |
$85 605 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $438 Cost: $1,877 |
$438 | 3,131 | - | - | - | - |
$438 3,131 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,790 Cost: $26,967 |
$5,664 | 40,457 | $2,126 | - | $6,000 | - | $5,664 40,457 kWh |
$2,126 - $ |
$6,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,438 Cost: $25,400 |
$5,438 | 38,842 | - | - | $6,000 | - | $5,438 38,842 kWh |
- - $ |
$6,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Personnel Changes | Electricity Usage | Electricity Fees | Personnel Changes |