Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Michigan State University |
---|---|
Assessment Year | 2023 |
Principal Product | Assembly Lines |
NAICS | 333249 - Other Industrial Machinery Manufacturing |
SIC | 3569 - General Industrial Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 380,000 |
Annual Production | 726,966 Pieces |
Production Hrs. Annual | 5,304 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $256,048 | 4,707,032 | kWh | $0.05 |
Electricity Demand | $252,864 | 10,700 | kW-months/year | $23.63 |
Electricity Fees | $744 | - | $ | - |
Natural Gas | $266,704 | 25,170 | MMBtu | $10.60 |
TOTAL ENERGY COSTS | $776,360 | |||
RECOMMENDED SAVINGS* | $407,021 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $263,985 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,416 Cost: $480 |
$1,651 | 33,019 | $1,765 | 75 | - | - | - | - |
$1,651 33,019 kWh |
$1,765 75 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $132,126 Cost: - |
$59,932 | 1,198,649 | $72,194 | 2,711 | - | - | - | - |
$59,932 1,198,649 kWh |
$72,194 2,711 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $517 Cost: $162 |
$517 | 10,333 | - | - | - | - | - | - |
$517 10,333 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $127,926 Cost: $136,639 |
$58,023 | 1,160,461 | $69,903 | 2,625 | - | - | - | - |
$58,023 1,160,461 kWh |
$69,903 2,625 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $504 Cost: $1,459 |
$475 | 9,504 | $29 | 1 | - | - | - | - |
$475 9,504 kWh |
$29 1 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $50,220 Cost: $250,000 |
$(-14,349) | (-286,981) | - | - | $64,569 | 7,465 | - | - |
$(-14,349) (-286,981) kWh |
- - kW-months/year |
$64,569 7,465 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $7,452 Cost: $496 |
$2,327 | 46,538 | - | - | $5,125 | 484 | - | - |
$2,327 46,538 kWh |
- - kW-months/year |
$5,125 484 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $406 Cost: $50 |
$124 | 2,482 | - | - | $282 | 27 | - | - |
$124 2,482 kWh |
- - kW-months/year |
$282 27 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $83,300 Cost: $13,599 |
$(-106) | (-2,127) | - | - | $83,406 | 7,876 | - | - |
$(-106) (-2,127) kWh |
- - kW-months/year |
$83,406 7,876 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $1,154 Cost: - |
- | - | - | - | - | - | $1,154 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,154 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $407,021 Cost: $402,885 |
$108,594 | 2,171,878 | $143,891 | 5,412 | $153,382 | 15,852 | $1,154 | - | $108,594 2,171,878 kWh |
$143,891 5,412 kW-months/year |
$153,382 15,852 MMBtu |
$1,154 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $263,985 Cost: $137,281 |
$120,123 | 2,402,462 | $143,862 | 5,411 | - | - | - | - | $120,123 2,402,462 kWh |
$143,862 5,411 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost |