Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Michigan State University |
---|---|
Assessment Year | 2023 |
Principal Product | Hydraulic Oil Filters and Components |
NAICS | 333999 - All Other Miscellaneous General Purpose Machinery Manufacturing |
SIC | 3569 - General Industrial Machinery, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 115,000 |
Annual Production | 1,500,000 Units |
Production Hrs. Annual | 6,552 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $201,007 | 2,340,147 | kWh | $0.09 |
Electricity Demand | $101,278 | 5,985 | kW-months/year | $16.92 |
Electricity Fees | $(-8,940) | - | $ | - |
Natural Gas | $23,139 | 2,694 | MMBtu | $8.59 |
TOTAL ENERGY COSTS | $316,483 | |||
RECOMMENDED SAVINGS* | $8,110 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,749 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,186 Cost: - |
$1,186 | 13,789 | - | - | - | - |
$1,186 13,789 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $2,322 Cost: - |
$2,322 | 27,003 | - | - | - | - |
$2,322 27,003 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,919 Cost: - |
$1,841 | 21,406 | $78 | 5 | - | - |
$1,841 21,406 kWh |
$78 5 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $138 Cost: $348 |
$138 | 1,606 | - | - | - | - |
$138 1,606 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $863 Cost: $112 |
$863 | 10,031 | - | - | - | - |
$863 10,031 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $643 Cost: $1,100 |
$643 | 7,477 | - | - | - | - |
$643 7,477 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $550 Cost: $776 |
$550 | 6,396 | - | - | - | - |
$550 6,396 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $490 Cost: $1,162 |
- | - | - | - | $490 | 57 |
- - kWh |
- - kW-months/year |
$490 57 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $8,110 Cost: $3,498 |
$7,543 | 87,708 | $78 | 5 | $490 | 57 | $7,543 87,708 kWh |
$78 5 kW-months/year |
$490 57 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,749 Cost: $1,560 |
$4,671 | 54,309 | $78 | 5 | - | - | $4,671 54,309 kWh |
$78 5 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |