IAC Assessment: MU0071
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MU0071
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Michigan State University
Assessment Year 2025
Principal Product Wood
NAICS 321113 - Sawmills
SIC 2421 - Sawmills And Planing Mills, General
Sales $10,000,000-$50,000,000
# of Employees 400
Plant Area (Sq.Ft.) 165,000
Annual Production 17,000,000 Units
Production Hrs. Annual 4,264
Location (State) MI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $395,098 4,927,832 kWh $0.08
Electricity Demand $217,201 27,807 kW-months/year $7.81
Electricity Fees $13,737 - $ -
Natural Gas $107,806 19,426 MMBtu $5.55
Fuel Oil #1 $19,255 931 MMBtu $20.67
Other Gas $2,889 1 MMBtu $2,889.00
TOTAL ENERGY COSTS $755,986
RECOMMENDED SAVINGS* $30,406 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Fuel Oil #1 Ancillary Material Cost Electricity Usage Electricity Demand Fuel Oil #1 Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT Savings:
$25,925
Cost:
$65,000
$(-1,076) (-13,451) $(-504) (-65) $19,255 931 $8,250 - $(-1,076)
(-13,451)
kWh
$(-504)
(-65)
kW-months/year
$19,255
931
MMBtu
$8,250
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,851
Cost:
$577
$2,514 31,431 $336 43 - - - - $2,514
31,431
kWh
$336
43
kW-months/year
-
-
MMBtu
-
-
$
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,188
Cost:
$3,637
$859 10,732 $330 42 - - - - $859
10,732
kWh
$330
42
kW-months/year
-
-
MMBtu
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$442
Cost:
$1,277
$323 4,032 $119 15 - - - - $323
4,032
kWh
$119
15
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$30,406
Cost:
$70,491
$2,619 32,744 $281 36 $19,255 931 $8,250 - $2,619
32,744
kWh
$281
36
kW-months/year
$19,255
931
MMBtu
$8,250
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Fuel Oil #1 Ancillary Material Cost Electricity Usage Electricity Demand Fuel Oil #1 Ancillary Material Cost