Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2007 |
Principal Product | electrica heaters and heating elements |
NAICS | 333414 - Heating Equipment (except Warm Air Furnaces) Manufacturing |
SIC | 3433 - Heating Equipment, Except Electric |
Sales | $1,000,000-$5,000,000 |
# of Employees | 86 |
Plant Area (Sq.Ft.) | 44,000 |
Annual Production | 60,000 Pieces |
Production Hrs. Annual | 5,100 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $48,188 | 1,273,128 | kWh | $0.04 |
Natural Gas | $42,973 | 3,780 | MMBtu | $11.37 |
TOTAL ENERGY COSTS | $91,161 | |||
RECOMMENDED SAVINGS* | $19,740 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,880 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $8,548 Cost: $2,135 |
$8,548 | 135,660 | - | - |
$8,548 135,660 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,880 Cost: $1,120 |
$6,880 | 27,293 | - | - |
$6,880 27,293 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT |
Savings: $4,312 Cost: $3,000 |
- | - | $4,312 | 379 |
- - kWh |
$4,312 379 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $19,740 Cost: $6,255 |
$15,428 | 162,953 | $4,312 | 379 | $15,428 162,953 kWh |
$4,312 379 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,880 Cost: $1,120 |
$6,880 | 27,293 | - | - | $6,880 27,293 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |