Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2012 |
Principal Product | zinc and plated fixtures |
NAICS | 332812 - Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479 - Metal Coating And Allied Services |
Sales | $50,000,000-$100,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 110,000 |
Annual Production | 300 Tons |
Production Hrs. Annual | 4,950 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $84,441 | 1,472,920 | kWh | $0.06 |
Electricity Demand | $22,028 | 4,901 | kW-months/year | $4.49 |
Natural Gas | $406,039 | 52,494 | MMBtu | $7.73 |
TOTAL ENERGY COSTS | $512,508 | |||
RECOMMENDED SAVINGS* | $156,643 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $154,995 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,648 Cost: $820 |
$1,388 | 23,137 | $260 | 58 | - | - |
$1,388 23,137 kWh |
$260 58 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $79,573 Cost: $6,500 |
- | - | - | - | $79,573 | 10,268 |
- - kWh |
- - kW-months/year |
$79,573 10,268 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $72,621 Cost: $8,500 |
- | - | - | - | $72,621 | 7,370 |
- - kWh |
- - kW-months/year |
$72,621 7,370 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,801 Cost: $8,200 |
$2,370 | 39,501 | $431 | 96 | - | - |
$2,370 39,501 kWh |
$431 96 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $156,643 Cost: $24,020 |
$3,758 | 62,638 | $691 | 154 | $152,194 | 17,638 | $3,758 62,638 kWh |
$691 154 kW-months/year |
$152,194 17,638 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $154,995 Cost: $23,200 |
$2,370 | 39,501 | $431 | 96 | $152,194 | 17,638 | $2,370 39,501 kWh |
$431 96 kW-months/year |
$152,194 17,638 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |