Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2013 |
Principal Product | vehicle frames and body |
NAICS | 336211 - Motor Vehicle Body Manufacturing |
SIC | 3711 - Motor Vehicles And Car Bodies |
Sales | $5,000,000-$10,000,000 |
# of Employees | 35 |
Plant Area (Sq.Ft.) | 70,000 |
Annual Production | 1,000 Pieces |
Production Hrs. Annual | 3,650 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $34,137 | 475,840 | kWh | $0.07 |
Electricity Demand | $18,600 | 1,861 | kW-months/year | $9.99 |
Natural Gas | $22,281 | 2,221 | MMBtu | $10.03 |
TOTAL ENERGY COSTS | $75,018 | |||
RECOMMENDED SAVINGS* | $7,383 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,383 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,108 Cost: $480 |
$1,108 | 15,384 | - | - |
$1,108 15,384 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,168 Cost: $9,300 |
$3,548 | 49,275 | $1,620 | 162 |
$3,548 49,275 kWh |
$1,620 162 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,107 Cost: $1,300 |
$758 | 10,522 | $349 | 35 |
$758 10,522 kWh |
$349 35 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $7,383 Cost: $11,080 |
$5,414 | 75,181 | $1,969 | 197 | $5,414 75,181 kWh |
$1,969 197 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,383 Cost: $11,080 |
$5,414 | 75,181 | $1,969 | 197 | $5,414 75,181 kWh |
$1,969 197 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |