Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2015 |
Principal Product | Bread, tortilla |
NAICS | 311812 - Commercial Bakeries |
SIC | 2045 - Prepared Flour Mixes And Doughs |
Sales | $50,000,000-$100,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 11,000,000 Pounds |
Production Hrs. Annual | 8,600 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,018,768 | 16,852,369 | kWh | $0.06 |
Electricity Demand | $449,942 | 33,851 | kW-months/year | $13.29 |
Natural Gas | $474,319 | 83,659 | MMBtu | $5.67 |
TOTAL ENERGY COSTS | $1,943,029 | |||
RECOMMENDED SAVINGS* | $160,155 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7425 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD |
Savings: $8,279 Cost: - |
$6,338 | 104,835 | $1,941 | 146 | - | - |
$6,338 104,835 kWh |
$1,941 146 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $22,758 Cost: $100,000 |
$22,758 | 376,462 | - | - | - | - |
$22,758 376,462 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $16,004 Cost: $6,500 |
$12,242 | 202,508 | $3,762 | 283 | - | - |
$12,242 202,508 kWh |
$3,762 283 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,923 Cost: $1,000 |
$1,471 | 24,335 | $452 | 34 | - | - |
$1,471 24,335 kWh |
$452 34 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $13,037 Cost: $1,560 |
$9,980 | 165,082 | $3,057 | 230 | - | - |
$9,980 165,082 kWh |
$3,057 230 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $62,569 Cost: $115,650 |
$47,882 | 792,060 | $14,687 | 1,105 | - | - |
$47,882 792,060 kWh |
$14,687 1,105 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $30,675 Cost: $7,500 |
$30,675 | 507,426 | - | - | - | - |
$30,675 507,426 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) |
Savings: $2,330 Cost: $3,500 |
- | - | - | - | $2,330 | 411 |
- - kWh |
- - kW-months/year |
$2,330 411 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,580 Cost: $9,500 |
- | - | - | - | $2,580 | 455 |
- - kWh |
- - kW-months/year |
$2,580 455 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $160,155 Cost: $245,210 |
$131,346 | 2,172,708 | $23,899 | 1,798 | $4,910 | 866 | $131,346 2,172,708 kWh |
$23,899 1,798 kW-months/year |
$4,910 866 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |