IAC Assessment: MZ0310
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MZ0310
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Missouri-Columbia
Assessment Year 2021
Principal Product Prefabricated Metal Buildings
NAICS 332311 - Prefabricated Metal Building and Component Manufacturing
SIC 3448 - Prefabricated Metal Buildings
Sales $10,000,000-$50,000,000
# of Employees 45
Plant Area (Sq.Ft.) 215,000
Annual Production 500 Units
Production Hrs. Annual 4,160
Location (State) KS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $84,224 881,028 kWh $0.10
Electricity Demand $17,414 2,785 kW-months/year $6.25
Electricity Fees $622 - $ -
Natural Gas $23,699 4,867 MMBtu $4.87
TOTAL ENERGY COSTS $125,959
RECOMMENDED SAVINGS* $13,319 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Administrative Changes Electricity Usage Electricity Demand Administrative Changes
$ kWh $ kW-months/year $ $
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$6,274
Cost:
$490
$6,274 65,624 - - - - $6,274
65,624
kWh
-
-
kW-months/year
-
-
$
02: 2.8115 BASE UTILITY CHARGES ON USAGE RATHER THAN AREA OCCUPIED Savings:
$3,630
Cost:
$1,160
- - - - $3,630 - -
-
kWh
-
-
kW-months/year
$3,630
-
$
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$2,250
Cost:
$2,580
- - $2,250 360 - - -
-
kWh
$2,250
360
kW-months/year
-
-
$
04: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$1,165
Cost:
$1,896
$1,069 11,178 $96 15 - - $1,069
11,178
kWh
$96
15
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$13,319
Cost:
$6,126
$7,343 76,802 $2,346 375 $3,630 - $7,343
76,802
kWh
$2,346
375
kW-months/year
$3,630
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Administrative Changes Electricity Usage Electricity Demand Administrative Changes