IAC Assessment: ND0316
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ND0316
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Notre Dame Univ.
Assessment Year 1998
Principal Product Trophies
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $10,000,000-$50,000,000
# of Employees 170
Plant Area (Sq.Ft.) 100,000
Annual Production 20,000,000 Pieces
Production Hrs. Annual 6,000
Location (State) IN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $214,337 4,008,793 kWh $0.05
Electricity Demand $82,578 8,581 kW-months/year $9.62
Natural Gas $55,600 11,431 MMBtu $4.86
TOTAL ENERGY COSTS $352,515
RECOMMENDED SAVINGS* $42,263 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,799
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (haz) Solid Waste (non-haz) Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (haz) Solid Waste (non-haz) Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ gal $ lb $ $ $ $
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$17,390
Cost:
$46,000
$(-3,823) (-71,512) $(-1,376) (-143) - - $22,589 4,648 - - - - - - - - $(-3,823)
(-71,512)
kWh
$(-1,376)
(-143)
kW-months/year
-
-
$
$22,589
4,648
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
02: 2.7229 AIR CONDITION ONLY SPACE NECESSARY Savings:
$8,600
Cost:
$37,000
$8,600 160,903 - - - - - - - - - - - - - - $8,600
160,903
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$602
Cost:
$80
$602 11,137 - - - - - - - - - - - - - - $602
11,137
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
04: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$4,665
Cost:
-
- - - - $4,665 - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
$4,665
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,167
Cost:
$9,920
$2,329 43,669 $838 87 - - - - - - - - - - - - $2,329
43,669
kWh
$838
87
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
06: 4.811 DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS Savings:
$2,075
Cost:
$250
- - - - - - - - - - - - $2,075 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
$2,075
-
$
-
-
$
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,405
Cost:
$250
- - - - - - $1,405 289 - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$1,405
289
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$1,335
Cost:
$600
$982 18,464 $353 37 - - - - - - - - - - - - $982
18,464
kWh
$353
37
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
09: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$794
Cost:
$150
$558 10,551 $236 24 - - - - - - - - - - - - $558
10,551
kWh
$236
24
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
10: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$617
Cost:
$363
$617 11,430 - - - - - - - - - - - - - - $617
11,430
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
11: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$485
Cost:
$400
$485 9,086 - - - - - - - - - - - - - - $485
9,086
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
12: 3.8211 CONVERT TO AQUEOUS CLEANING SYSTEM Savings:
$393
Cost:
$200
- - - - - - - - $393 3,768 - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$393
3,768
gal
-
-
lb
-
-
$
-
-
$
13: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$342
Cost:
$550
$132 2,345 $33 3 - - - - - - - - - - $177 - $132
2,345
kWh
$33
3
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
$177
-
$
14: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$393
Cost:
$60
- - - - - - - - - - $393 4,800 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
gal
$393
4,800
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$42,263
Cost:
$95,823
$10,482 196,073 $84 8 $4,665 - $23,994 4,937 $393 3,768 $393 4,800 $2,075 - $177 - $10,482
196,073
kWh
$84
8
kW-months/year
$4,665
-
$
$23,994
4,937
MMBtu
$393
3,768
gal
$393
4,800
lb
$2,075
-
$
$177
-
$
TOTAL IMPLEMENTED Savings:
$8,799
Cost:
$1,453
$2,759 51,582 $589 61 $4,665 - - - $393 3,768 $393 4,800 - - - - $2,759
51,582
kWh
$589
61
kW-months/year
$4,665
-
$
-
-
MMBtu
$393
3,768
gal
$393
4,800
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ gal $ lb $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (haz) Solid Waste (non-haz) Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Other Liquid (haz) Solid Waste (non-haz) Administrative Changes Ancillary Material Cost