Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Notre Dame Univ. |
---|---|
Assessment Year | 1999 |
Principal Product | Electromagnetic Coils |
NAICS | n/a |
SIC | 3677 - Electronic Coils And Transformers |
Sales | $10,000,000-$50,000,000 |
# of Employees | 135 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 1,000 Thousand Feet |
Production Hrs. Annual | 6,240 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $57,075 | 1,620,164 | kWh | $0.04 |
Electricity Demand | $36,850 | 5,955 | kW-months/year | $6.19 |
Natural Gas | $11,385 | 2,320 | MMBtu | $4.91 |
TOTAL ENERGY COSTS | $105,310 | |||
RECOMMENDED SAVINGS* | $7,121 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $912 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | LPG | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | LPG | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,025 Cost: $10,705 |
$3,894 | 111,665 | $1,131 | 15 | - | - | - | - | - | - |
$3,894 111,665 kWh |
$1,131 15 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $63 Cost: $65 |
$63 | 1,758 | - | - | - | - | - | - | - | - |
$63 1,758 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7145 INSTALL SKYLIGHTS |
Savings: $535 Cost: $420 |
$99 | 2,052 | - | - | $436 | 89 | - | - | - | - |
$99 2,052 kWh |
- - kW-months/year |
$436 89 MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $411 Cost: $30 |
$306 | 8,792 | $105 | 17 | - | - | - | - | - | - |
$306 8,792 kWh |
$105 17 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $380 Cost: $440 |
$191 | 5,569 | $47 | 8 | - | - | - | - | $142 | - |
$191 5,569 kWh |
$47 8 kW-months/year |
- - MMBtu |
- - MMBtu |
$142 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $155 Cost: $40 |
$115 | 3,224 | $40 | 6 | - | - | - | - | - | - |
$115 3,224 kWh |
$40 6 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $283 Cost: $510 |
$149 | 4,396 | $223 | 36 | $(-89) | (-18) | - | - | - | - |
$149 4,396 kWh |
$223 36 kW-months/year |
$(-89) (-18) MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $269 Cost: $450 |
$114 | 3,224 | $223 | 36 | - | - | $(-68) | (-14) | - | - |
$114 3,224 kWh |
$223 36 kW-months/year |
- - MMBtu |
$(-68) (-14) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $7,121 Cost: $12,660 |
$4,931 | 140,680 | $1,769 | 118 | $347 | 71 | $(-68) | (-14) | $142 | - | $4,931 140,680 kWh |
$1,769 118 kW-months/year |
$347 71 MMBtu |
$(-68) (-14) MMBtu |
$142 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $912 Cost: $645 |
$633 | 18,170 | $368 | 59 | $(-89) | (-18) | - | - | - | - | $633 18,170 kWh |
$368 59 kW-months/year |
$(-89) (-18) MMBtu |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | LPG | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | LPG | Ancillary Material Cost |