IAC Assessment: ND0325
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ND0325
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Notre Dame Univ.
Assessment Year 1999
Principal Product Electric Transformers
NAICS n/a
SIC 3612 - Transformers, Except Electronic
Sales $10,000,000-$50,000,000
# of Employees 150
Plant Area (Sq.Ft.) 54,000
Annual Production 6,000,000 Pieces
Production Hrs. Annual 4,420
Location (State) IN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $36,442 2,218,933 kWh $0.02
Electricity Demand $58,179 5,331 kW-months/year $10.91
Natural Gas $25,016 4,113 MMBtu $6.08
TOTAL ENERGY COSTS $119,637
RECOMMENDED SAVINGS* $9,158 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,420
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ lb $ $
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$641
Cost:
$1,000
$233 13,775 $408 37 - - - - - - $233
13,775
kWh
$408
37
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
02: 2.1135 REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY Savings:
$232
Cost:
$130
- - - - $232 38 - - - - -
-
kWh
-
-
kW-months/year
$232
38
MMBtu
-
-
lb
-
-
$
03: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$6,626
Cost:
$10,000
$2,412 142,145 $4,214 386 - - - - - - $2,412
142,145
kWh
$4,214
386
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
04: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP Savings:
$97
Cost:
$80
$35 2,052 $62 6 - - - - - - $35
2,052
kWh
$62
6
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$299
Cost:
$190
$109 6,448 $190 17 - - - - - - $109
6,448
kWh
$190
17
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$248
Cost:
$80
$248 14,654 - - - - - - - - $248
14,654
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
07: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$720
Cost:
$20
- - - - - - $720 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$720
-
lb
-
-
$
08: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$295
Cost:
-
- - - - - - - - $295 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$295
-
$
TOTAL RECOMMENDED Savings:
$9,158
Cost:
$11,500
$3,037 179,074 $4,874 446 $232 38 $720 - $295 - $3,037
179,074
kWh
$4,874
446
kW-months/year
$232
38
MMBtu
$720
-
lb
$295
-
$
TOTAL IMPLEMENTED Savings:
$8,420
Cost:
$10,420
$2,769 163,247 $4,404 403 $232 38 $720 - $295 - $2,769
163,247
kWh
$4,404
403
kW-months/year
$232
38
MMBtu
$720
-
lb
$295
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Administrative Changes