IAC Assessment: ND0345
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ND0345
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Notre Dame Univ.
Assessment Year 2000
Principal Product Fiber Board
NAICS n/a
SIC 2631 - Paperboard Mills
Sales $10,000,000-$50,000,000
# of Employees 75
Plant Area (Sq.Ft.) 160,000
Annual Production 5,000 Thousand Feet
Production Hrs. Annual 2,210
Location (State) MI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $117,963 2,283,998 kWh $0.05
Electricity Demand $19,511 6,155 kW-months/year $3.17
TOTAL ENERGY COSTS $137,474
RECOMMENDED SAVINGS* $6,459 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,882
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $ $ $ $ $ $ $
01: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$386
Cost:
-
$386 7,620 - - - - - - - - - - - - $386
7,620
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$587
Cost:
$590
$179 3,517 $15 5 - - $270 - - - $123 - - - $179
3,517
kWh
$15
5
kW-months/year
-
-
$
$270
-
$
-
-
$
$123
-
$
-
-
$
03: 2.7134 USE PHOTOCELL CONTROLS Savings:
$124
Cost:
$350
$93 1,758 $31 10 - - - - - - - - - - $93
1,758
kWh
$31
10
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$862
Cost:
$6,560
$649 12,603 $213 67 - - - - - - - - - - $649
12,603
kWh
$213
67
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
-
-
$
05: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD Savings:
$913
Cost:
-
$442 8,499 $221 70 - - - - $250 - - - - - $442
8,499
kWh
$221
70
kW-months/year
-
-
$
-
-
$
$250
-
$
-
-
$
-
-
$
06: 4.4250 ELIMINATE/REDUCE REDUNDANT INSPECTIONS Savings:
$134
Cost:
-
- - - - - - $134 - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$134
-
$
-
-
$
-
-
$
-
-
$
07: 2.3511 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS Savings:
$2,211
Cost:
$200
- - - - $(-3,585) - - - - - - - $5,796 - -
-
kWh
-
-
kW-months/year
$(-3,585)
-
$
-
-
$
-
-
$
-
-
$
$5,796
-
$
08: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$1,242
Cost:
$250
- - - - $1,242 - - - - - - - - - -
-
kWh
-
-
kW-months/year
$1,242
-
$
-
-
$
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$6,459
Cost:
$7,950
$1,749 33,997 $480 152 $(-2,343) - $404 - $250 - $123 - $5,796 - $1,749
33,997
kWh
$480
152
kW-months/year
$(-2,343)
-
$
$404
-
$
$250
-
$
$123
-
$
$5,796
-
$
TOTAL IMPLEMENTED Savings:
$2,882
Cost:
$7,150
$1,656 32,239 $449 142 - - $404 - $250 - $123 - - - $1,656
32,239
kWh
$449
142
kW-months/year
-
-
$
$404
-
$
$250
-
$
$123
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost One-time Revenue or Avoided Cost