Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nebraska–Lincoln |
---|---|
Assessment Year | 2019 |
Principal Product | Mining Equipment |
NAICS | 333131 - Mining Machinery and Equipment Manufacturing |
SIC | 3532 - Mining Machinery |
Sales | $10,000,000-$50,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 210,000 |
Annual Production | 408 Units |
Production Hrs. Annual | 4,966 |
Location (State) | SD |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $73,187 | 1,876,600 | kWh | $0.04 |
Electricity Demand | $105,725 | 8,084 | kW-months/year | $13.08 |
Electricity Fees | $960 | - | $ | - |
Natural Gas | $59,012 | 11,689 | MMBtu | $5.05 |
TOTAL ENERGY COSTS | $240,170 | |||
RECOMMENDED SAVINGS* | $65,802 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $48,867 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Increase in Production | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $36,555 Cost: $34,820 |
$20,545 | 525,249 | $16,010 | 1,224 | - | - | - | - | - | - | - | - |
$20,545 525,249 kWh |
$16,010 1,224 kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $16,935 Cost: $18,980 |
$(-597) | (-15,308) | $(-468) | (-36) | - | - | - | - | - | - | $18,000 | - |
$(-597) (-15,308) kWh |
$(-468) (-36) kW-months/year |
- - $ |
- - $ |
- - $ |
$18,000 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $8,170 Cost: $35,828 |
$3,572 | 91,581 | $4,598 | 352 | - | - | - | - | - | - | - | - |
$3,572 91,581 kWh |
$4,598 352 kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $1,867 Cost: - |
- | - | - | - | - | - | - | - | $1,867 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$1,867 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,450 Cost: $1,600 |
$1,670 | 42,850 | - | - | $(-120) | - | $(-100) | - | - | - | - | - |
$1,670 42,850 kWh |
- - kW-months/year |
$(-120) - $ |
$(-100) - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $825 Cost: $2,025 |
$825 | 21,159 | - | - | - | - | - | - | - | - | - | - |
$825 21,159 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $65,802 Cost: $93,253 |
$26,015 | 665,531 | $20,140 | 1,540 | $(-120) | - | $(-100) | - | $1,867 | - | $18,000 | - | $26,015 665,531 kWh |
$20,140 1,540 kW-months/year |
$(-120) - $ |
$(-100) - $ |
$1,867 - $ |
$18,000 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $48,867 Cost: $74,273 |
$26,612 | 680,839 | $20,608 | 1,576 | $(-120) | - | $(-100) | - | $1,867 | - | - | - | $26,612 680,839 kWh |
$20,608 1,576 kW-months/year |
$(-120) - $ |
$(-100) - $ |
$1,867 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Increase in Production | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Increase in Production |