Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nebraska–Lincoln |
---|---|
Assessment Year | 2022 |
Principal Product | Precast Concrete |
NAICS | 327390 - Other Concrete Product Manufacturing |
SIC | 3272 - Concrete Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 80 |
Plant Area (Sq.Ft.) | 1,450,000 |
Annual Production | 10,503 Thousand Gallons |
Production Hrs. Annual | 3,120 |
Location (State) | NE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $63,840 | 978,584 | kWh | $0.07 |
Electricity Demand | $24,205 | 4,499 | kW-months/year | $5.38 |
Electricity Fees | $2,297 | - | $ | - |
Natural Gas | $65,557 | 17,176 | MMBtu | $3.82 |
Other Gas | $29,503 | 1 | MMBtu | $29,503.00 |
TOTAL ENERGY COSTS | $185,402 | |||
RECOMMENDED SAVINGS* | $6,114 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,101 Cost: $2,000 |
$2,881 | 44,188 | - | - | $(-680) | - | - | - | $(-100) | - |
$2,881 44,188 kWh |
- - kW-months/year |
$(-680) - $ |
- - $ |
$(-100) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,901 Cost: $3,265 |
$1,342 | 20,579 | $429 | 80 | $131 | - | - | - | - | - |
$1,342 20,579 kWh |
$429 80 kW-months/year |
$131 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,230 Cost: $2,400 |
$1,028 | 15,768 | $181 | 34 | $21 | - | - | - | - | - |
$1,028 15,768 kWh |
$181 34 kW-months/year |
$21 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $505 Cost: $2,425 |
$505 | 7,740 | - | - | - | - | - | - | - | - |
$505 7,740 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $377 Cost: $85 |
- | - | - | - | - | - | $377 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$377 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $6,114 Cost: $10,175 |
$5,756 | 88,275 | $609 | 113 | $(-528) | - | $377 | - | $(-100) | - | $5,756 88,275 kWh |
$609 113 kW-months/year |
$(-528) - $ |
$377 - $ |
$(-100) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost |