Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nebraska–Lincoln |
---|---|
Assessment Year | 2023 |
Principal Product | Excavation and Mining Equipment |
NAICS | 333131 - Mining Machinery and Equipment Manufacturing |
SIC | 3532 - Mining Machinery |
Sales | $100,000,000-$500,000,000 |
# of Employees | 450 |
Plant Area (Sq.Ft.) | 360,000 |
Annual Production | 95 Units |
Production Hrs. Annual | 6,864 |
Location (State) | SD |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $294,483 | 5,222,750 | kWh | $0.06 |
Electricity Demand | $197,992 | 15,736 | kW-months/year | $12.58 |
Electricity Fees | $31,402 | - | $ | - |
Natural Gas | $213,415 | 60,103 | MMBtu | $3.55 |
TOTAL ENERGY COSTS | $751,109 | |||
RECOMMENDED SAVINGS* | $319,149 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $129,701 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.112 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL |
Savings: $150,762 Cost: $690,000 |
$(-1,129) | (-20,160) | - | - | - | - | $4,200 | - | - | - | - | - | $147,691 | - |
$(-1,129) (-20,160) kWh |
- - kW-months/year |
- - MMBtu |
$4,200 - $ |
- - $ |
- - $ |
$147,691 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $121,895 Cost: $4,200 |
- | - | - | - | - | - | $9,435 | - | $116,660 | - | $(-4,200) | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$9,435 - $ |
$116,660 - $ |
$(-4,200) - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $36,689 Cost: $350 |
- | - | $36,689 | 2,916 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$36,689 2,916 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,279 Cost: $4,500 |
$7,939 | 141,768 | - | - | - | - | $(-560) | - | $(-100) | - | - | - | - | - |
$7,939 141,768 kWh |
- - kW-months/year |
- - MMBtu |
$(-560) - $ |
$(-100) - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $1,997 Cost: $470 |
- | - | - | - | $1,997 | 563 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,997 563 MMBtu |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $527 Cost: $200 |
- | - | - | - | $527 | 149 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$527 149 MMBtu |
- - $ |
- - $ |
- - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $319,149 Cost: $699,720 |
$6,810 | 121,608 | $36,689 | 2,916 | $2,524 | 711 | $13,075 | - | $116,560 | - | $(-4,200) | - | $147,691 | - | $6,810 121,608 kWh |
$36,689 2,916 kW-months/year |
$2,524 711 MMBtu |
$13,075 - $ |
$116,560 - $ |
$(-4,200) - $ |
$147,691 - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $129,701 Cost: $8,900 |
$7,939 | 141,768 | - | - | $527 | 149 | $8,875 | - | $116,560 | - | $(-4,200) | - | - | - | $7,939 141,768 kWh |
- - kW-months/year |
$527 149 MMBtu |
$8,875 - $ |
$116,560 - $ |
$(-4,200) - $ |
- - % |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | One-time Revenue or Avoided Cost | Increase in Production |