Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of North Texas |
---|---|
Assessment Year | 2023 |
Principal Product | metal stamping products |
NAICS | 336370 - Motor Vehicle Metal Stamping |
SIC | 3469 - Metal Stampings, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 16,594,601 Units |
Production Hrs. Annual | 5,200 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $169,883 | 2,159,800 | kWh | $0.08 |
Electricity Demand | $66,666 | 6,666 | kW-months/year | $10.00 |
Electricity Fees | $2,400 | - | $ | - |
Natural Gas | $2,328 | 153 | MMBtu | $15.20 |
TOTAL ENERGY COSTS | $241,278 | |||
RECOMMENDED SAVINGS* | $136,151 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $25,455 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $9,414 Cost: $5,801 |
$7,265 | 93,137 | $2,149 | 215 | - | - |
$7,265 93,137 kWh |
$2,149 215 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $14,389 Cost: $21,853 |
- | - | $14,389 | 1,439 | - | - |
- - kWh |
$14,389 1,439 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,026 Cost: $2,499 |
$599 | 7,679 | $427 | 43 | - | - |
$599 7,679 kWh |
$427 43 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $1,504 Cost: - |
$1,504 | 19,284 | - | - | - | - |
$1,504 19,284 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.1161 ELIMINATE/REDUCE AN OPERATION |
Savings: $9,631 Cost: - |
$7,432 | 95,280 | $2,199 | 220 | - | - |
$7,432 95,280 kWh |
$2,199 220 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.446 AUTOMATE FINISHING PROCESS |
Savings: $96,307 Cost: $111,000 |
- | - | - | - | $96,307 | - |
- - kWh |
- - kW-months/year |
$96,307 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7425 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD |
Savings: $3,880 Cost: $7,474 |
$2,240 | 28,718 | $1,640 | 164 | - | - |
$2,240 28,718 kWh |
$1,640 164 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $136,151 Cost: $148,627 |
$19,040 | 244,098 | $20,805 | 2,081 | $96,307 | - | $19,040 244,098 kWh |
$20,805 2,081 kW-months/year |
$96,307 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $25,455 Cost: $15,774 |
$19,040 | 244,098 | $6,415 | 642 | - | - | $19,040 244,098 kWh |
$6,415 642 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes |