Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of North Texas |
---|---|
Assessment Year | 2023 |
Principal Product | Coating, Engraving and Allied Services |
NAICS | 332812 - Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479 - Metal Coating And Allied Services |
Sales | $10,000,000-$50,000,000 |
# of Employees | 81 |
Plant Area (Sq.Ft.) | 771,012 |
Annual Production | 66,769,477 Pounds |
Production Hrs. Annual | 5,184 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $108,984 | 1,586,593 | kWh | $0.07 |
Electricity Demand | $47,204 | 3,669 | kW-months/year | $12.87 |
Electricity Fees | $2,301 | - | $ | - |
Natural Gas | $287,848 | 71,448 | MMBtu | $4.03 |
TOTAL ENERGY COSTS | $446,336 | |||
RECOMMENDED SAVINGS* | $135,620 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $35,420 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,361 Cost: $4,553 |
$1,647 | 23,967 | $714 | 55 | - | - | - | - |
$1,647 23,967 kWh |
$714 55 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $35,653 Cost: $1,258 |
- | - | - | - | $35,653 | 8,913 | - | - |
- - kWh |
- - kW-months/year |
$35,653 8,913 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,450 Cost: $1,311 |
- | - | - | - | $1,450 | 360 | - | - |
- - kWh |
- - kW-months/year |
$1,450 360 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $35,420 Cost: $11,457 |
$28,187 | 410,290 | $7,233 | 562 | - | - | - | - |
$28,187 410,290 kWh |
$7,233 562 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,528 Cost: - |
$2,461 | 35,824 | $1,067 | 83 | - | - | - | - |
$2,461 35,824 kWh |
$1,067 83 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $8,460 Cost: $6,082 |
- | - | $8,460 | 658 | - | - | - | - |
- - kWh |
$8,460 658 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.231 PURCHASE EQUIPMENT INSTEAD OF LEASING |
Savings: $45,600 Cost: $27,500 |
- | - | - | - | - | - | $45,600 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$45,600 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $1,056 Cost: - |
$1,056 | 15,372 | - | - | - | - | - | - |
$1,056 15,372 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,092 Cost: $5,443 |
$1,080 | 15,725 | $1,012 | 79 | - | - | - | - |
$1,080 15,725 kWh |
$1,012 79 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $135,620 Cost: $57,604 |
$34,431 | 501,178 | $18,486 | 1,437 | $37,103 | 9,273 | $45,600 | - | $34,431 501,178 kWh |
$18,486 1,437 kW-months/year |
$37,103 9,273 MMBtu |
$45,600 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $35,420 Cost: $11,457 |
$28,187 | 410,290 | $7,233 | 562 | - | - | - | - | $28,187 410,290 kWh |
$7,233 562 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost |