IAC Assessment: NT0020
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NT0020
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of North Texas
Assessment Year 2024
Principal Product helicopter blades
NAICS 336413 - Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728 - Aircraft Parts And Equipment, Nec
Sales $100,000,000-$500,000,000
# of Employees 180
Plant Area (Sq.Ft.) 160,000
Annual Production 1,200 Pieces
Production Hrs. Annual 5,356
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $516,683 6,060,235 kWh $0.09
Electricity Demand $266,665 13,536 kW-months/year $19.70
Electricity Fees $45,795 - $ -
Natural Gas $242,913 23,419 MMBtu $10.37
TOTAL ENERGY COSTS $1,072,056
RECOMMENDED SAVINGS* $258,309 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $80,204
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$9,491
Cost:
$4,553
$6,254 73,322 $3,236 164 - - - - $6,254
73,322
kWh
$3,236
164
kW-months/year
-
-
MMBtu
-
-
$
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$18,251
Cost:
-
$12,027 141,001 $6,223 316 - - - - $12,027
141,001
kWh
$6,223
316
kW-months/year
-
-
MMBtu
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$33,277
Cost:
$33,920
$21,930 257,088 $11,347 576 - - - - $21,930
257,088
kWh
$11,347
576
kW-months/year
-
-
MMBtu
-
-
$
04: 2.2511 INSULATE BARE EQUIPMENT Savings:
$3,147
Cost:
$11,909
- - - - $3,147 303 - - -
-
kWh
-
-
kW-months/year
$3,147
303
MMBtu
-
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$27,816
Cost:
$16,551
$18,331 214,905 $9,485 482 - - - - $18,331
214,905
kWh
$9,485
482
kW-months/year
-
-
MMBtu
-
-
$
06: 4.812 APPLY FOR INVESTMENT INCENTIVES Savings:
$52,462
Cost:
-
- - - - - - $52,462 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$52,462
-
$
07: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$113,865
Cost:
$96,040
$9,137 107,120 $4,728 240 - - $100,000 - $9,137
107,120
kWh
$4,728
240
kW-months/year
-
-
MMBtu
$100,000
-
$
TOTAL RECOMMENDED Savings:
$258,309
Cost:
$162,973
$67,680 793,436 $35,020 1,778 $3,147 303 $152,462 - $67,680
793,436
kWh
$35,020
1,778
kW-months/year
$3,147
303
MMBtu
$152,462
-
$
TOTAL IMPLEMENTED Savings:
$80,204
Cost:
$4,553
$18,282 214,323 $9,460 480 - - $52,462 - $18,282
214,323
kWh
$9,460
480
kW-months/year
-
-
MMBtu
$52,462
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost