IAC Assessment: NV0043
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NV0043
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Nevada
Assessment Year 1995
Principal Product Aircraft Lighting Systems
NAICS n/a
SIC 3647 - Vehicular Lighting Equipment
Sales $10,000,000-$50,000,000
# of Employees 250
Plant Area (Sq.Ft.) 150,000
Annual Production 28,000 Pieces
Production Hrs. Annual 2,210
Location (State) NV
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $117,206 1,616,354 kWh $0.07
Natural Gas $22,862 3,801 MMBtu $6.01
TOTAL ENERGY COSTS $140,068
RECOMMENDED SAVINGS* $11,664 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $7,897
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$171
Cost:
$120
$171 3,810 - - $171
3,810
kWh
-
-
MMBtu
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$563
Cost:
$553
- - $563 97 -
-
kWh
$563
97
MMBtu
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$3,295
Cost:
$10,075
- - $3,295 654 -
-
kWh
$3,295
654
MMBtu
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,536
Cost:
$2,050
$3,536 44,256 - - $3,536
44,256
kWh
-
-
MMBtu
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$231
Cost:
$259
$231 4,396 - - $231
4,396
kWh
-
-
MMBtu
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$3,277
Cost:
$700
$3,277 43,669 - - $3,277
43,669
kWh
-
-
MMBtu
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$591
Cost:
$200
$591 12,603 - - $591
12,603
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$11,664
Cost:
$13,957
$7,806 108,734 $3,858 751 $7,806
108,734
kWh
$3,858
751
MMBtu
TOTAL IMPLEMENTED Savings:
$7,897
Cost:
$11,648
$4,039 60,082 $3,858 751 $4,039
60,082
kWh
$3,858
751
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas