Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nevada |
---|---|
Assessment Year | 1996 |
Principal Product | custom compounded plastic resins |
NAICS | n/a |
SIC | 3087 - Custom Compound Purchased Resins |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 7,000,000 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | NV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $121,521 | 2,700,762 | kWh | $0.04 |
Electricity Demand | $61,316 | 7,795 | kW-months/year | $7.87 |
Electricity Fees | $5,463 | - | $ | - |
Natural Gas | $12,488 | 2,207 | MMBtu | $5.66 |
TOTAL ENERGY COSTS | $200,893 | |||
RECOMMENDED SAVINGS* | $13,816 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,694 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $1,263 Cost: $3,525 |
- | - | - | - | $1,263 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,263 - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $1,698 Cost: $4,225 |
- | - | - | - | - | - | $1,698 | 341 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,698 341 MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $7,602 Cost: $21,840 |
$4,951 | 109,906 | $2,651 | 374 | - | - | - | - | - | - |
$4,951 109,906 kWh |
$2,651 374 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $513 Cost: $260 |
$513 | 11,430 | - | - | - | - | - | - | - | - |
$513 11,430 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,300 Cost: $600 |
$1,300 | 29,015 | - | - | - | - | - | - | - | - |
$1,300 29,015 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $438 Cost: $100 |
$438 | 9,965 | - | - | - | - | - | - | - | - |
$438 9,965 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $394 Cost: $25 |
$281 | 7,620 | $113 | 14 | - | - | - | - | - | - |
$281 7,620 kWh |
$113 14 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $503 Cost: $164 |
$423 | 9,379 | $80 | 10 | - | - | - | - | - | - |
$423 9,379 kWh |
$80 10 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $105 Cost: $30 |
- | - | - | - | - | - | - | - | $105 | 6,500 |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$105 6,500 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,816 Cost: $30,769 |
$7,906 | 177,315 | $2,844 | 398 | $1,263 | - | $1,698 | 341 | $105 | 6,500 | $7,906 177,315 kWh |
$2,844 398 kW-months/year |
$1,263 - $ |
$1,698 341 MMBtu |
$105 6,500 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,694 Cost: $625 |
$1,581 | 36,635 | $113 | 14 | - | - | - | - | - | - | $1,581 36,635 kWh |
$113 14 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) |