Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nevada |
---|---|
Assessment Year | 1997 |
Principal Product | Concrete |
NAICS | n/a |
SIC | 3273 - Ready-mixed Concrete |
Sales | $5,000,000-$10,000,000 |
# of Employees | 18 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 500,000 Tons |
Production Hrs. Annual | 2,340 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $137,639 | 1,267,878 | kWh | $0.11 |
Electricity Demand | $22,071 | 23,571 | kW-months/year | $0.94 |
Electricity Fees | $3,930 | - | $ | - |
TOTAL ENERGY COSTS | $163,640 | |||
RECOMMENDED SAVINGS* | $8,719 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $246 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $246 Cost: $120 |
$233 | 3,810 | $13 | 4 | - | - |
$233 3,810 kWh |
$13 4 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $7,226 Cost: $6,404 |
$6,878 | 38,394 | $348 | 110 | - | - |
$6,878 38,394 kWh |
$348 110 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $1,247 Cost: $3,460 |
- | - | - | - | $1,247 | - |
- - kWh |
- - kW-months/year |
$1,247 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $8,719 Cost: $9,984 |
$7,111 | 42,204 | $361 | 114 | $1,247 | - | $7,111 42,204 kWh |
$361 114 kW-months/year |
$1,247 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $246 Cost: $120 |
$233 | 3,810 | $13 | 4 | - | - | $233 3,810 kWh |
$13 4 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees |