Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nevada |
---|---|
Assessment Year | 1998 |
Principal Product | Ready Mix Concrete |
NAICS | n/a |
SIC | 3273 - Ready-mixed Concrete |
Sales | $10,000,000-$50,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 200,000 Units |
Production Hrs. Annual | 4,623 |
Location (State) | NV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $8,514 | 191,676 | kWh | $0.04 |
Electricity Demand | $18,514 | 1,937 | kW-months/year | $9.56 |
Electricity Fees | $1,869 | - | $ | - |
Natural Gas | $31,240 | 6,026 | MMBtu | $5.18 |
TOTAL ENERGY COSTS | $60,137 | |||
RECOMMENDED SAVINGS* | $72,516 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,823 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $686 Cost: $550 |
- | - | - | - | - | - | $686 | 133 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$686 133 MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,687 Cost: $1,076 |
$871 | 20,809 | $782 | 84 | $34 | - | - | - | - | - | - | - | - | - | - | - | - | - |
$871 20,809 kWh |
$782 84 kW-months/year |
$34 - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $3,155 Cost: $4,348 |
$1,646 | 39,273 | $1,447 | 156 | $62 | - | - | - | - | - | - | - | - | - | - | - | - | - |
$1,646 39,273 kWh |
$1,447 156 kW-months/year |
$62 - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,204 Cost: - |
$1,370 | 32,825 | $791 | 85 | $43 | - | - | - | - | - | - | - | - | - | - | - | - | - |
$1,370 32,825 kWh |
$791 85 kW-months/year |
$43 - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $349 Cost: $150 |
$84 | 2,052 | $241 | 26 | $24 | - | - | - | - | - | - | - | - | - | - | - | - | - |
$84 2,052 kWh |
$241 26 kW-months/year |
$24 - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $776 Cost: $157 |
$483 | 11,430 | $278 | 30 | $15 | - | - | - | - | - | - | - | - | - | - | - | - | - |
$483 11,430 kWh |
$278 30 kW-months/year |
$15 - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $353 Cost: - |
$225 | 5,275 | $121 | 13 | $7 | - | - | - | - | - | - | - | - | - | - | - | - | - |
$225 5,275 kWh |
$121 13 kW-months/year |
$7 - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.112 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL |
Savings: $6,552 Cost: $233 |
- | - | - | - | - | - | - | - | - | - | - | - | $6,552 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
$6,552 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $15,147 Cost: $60,500 |
- | - | - | - | - | - | - | - | - | - | - | - | $15,147 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
$15,147 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES |
Savings: $120 Cost: $150 |
- | - | - | - | - | - | - | - | $120 | 54,750 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$120 54,750 Tgal |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.5314 USE IN-PROCESS RECYCLING WHENEVER POSSIBLE |
Savings: $4,175 Cost: $40,550 |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | $4,175 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
$4,175 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $35,819 Cost: $1,000 |
- | - | - | - | - | - | - | - | $2,981 | 1,365,000 | - | - | $64,260 | - | - | - | $(-31,422) | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$2,981 1,365,000 Tgal |
- - lb |
$64,260 - $ |
- - $ |
$(-31,422) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $1,493 Cost: - |
- | - | - | - | - | - | - | - | - | - | $1,493 | 2,280 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
$1,493 2,280 lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $72,516 Cost: $108,714 |
$4,679 | 111,664 | $3,660 | 394 | $185 | - | $686 | 133 | $3,101 | 1,419,750 | $1,493 | 2,280 | $85,959 | - | $4,175 | - | $(-31,422) | - | $4,679 111,664 kWh |
$3,660 394 kW-months/year |
$185 - $ |
$686 133 MMBtu |
$3,101 1,419,750 Tgal |
$1,493 2,280 lb |
$85,959 - $ |
$4,175 - $ |
$(-31,422) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,823 Cost: $6,431 |
$4,679 | 111,664 | $3,660 | 394 | $185 | - | $686 | 133 | $120 | 54,750 | $1,493 | 2,280 | - | - | - | - | - | - | $4,679 111,664 kWh |
$3,660 394 kW-months/year |
$185 - $ |
$686 133 MMBtu |
$120 54,750 Tgal |
$1,493 2,280 lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost |