Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nevada |
---|---|
Assessment Year | 1999 |
Principal Product | Newspapers |
NAICS | n/a |
SIC | 2711 - Newspapers |
Sales | $5,000,000-$10,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 18,000 |
Annual Production | 5,304,000 Pieces |
Production Hrs. Annual | 3,744 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $35,162 | 427,608 | kWh | $0.08 |
Electricity Demand | $6,635 | 1,529 | kW-months/year | $4.34 |
Electricity Fees | $986 | - | $ | - |
Natural Gas | $4,979 | 749 | MMBtu | $6.65 |
TOTAL ENERGY COSTS | $47,762 | |||
RECOMMENDED SAVINGS* | $119,408 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $93,329 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Administrative Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Administrative Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $640 Cost: $640 |
$475 | 5,862 | $165 | 38 | - | - | - | - | - | - | - | - |
$475 5,862 kWh |
$165 38 kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $354 Cost: $110 |
$353 | 4,396 | - | - | $1 | - | - | - | - | - | - | - |
$353 4,396 kWh |
- - kW-months/year |
$1 - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $158 Cost: - |
$105 | 1,172 | $53 | 12 | - | - | - | - | - | - | - | - |
$105 1,172 kWh |
$53 12 kW-months/year |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $701 Cost: $825 |
$470 | 5,862 | $230 | 53 | $1 | - | - | - | - | - | - | - |
$470 5,862 kWh |
$230 53 kW-months/year |
$1 - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,223 Cost: $6,789 |
$4,500 | 54,807 | $712 | 164 | $11 | - | - | - | - | - | - | - |
$4,500 54,807 kWh |
$712 164 kW-months/year |
$11 - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT |
Savings: $24,200 Cost: $102,400 |
- | - | - | - | - | - | - | - | $24,200 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$24,200 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $860 Cost: - |
- | - | - | - | - | - | - | - | $860 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$860 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.8214 USE WATER-BASED DEVELOPERS AND FINISHERS |
Savings: $160 Cost: - |
- | - | - | - | - | - | - | - | $160 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$160 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $74,476 Cost: $250,000 |
- | - | - | - | - | - | - | - | $20,476 | - | $54,000 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$20,476 - $ |
$54,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $12,636 Cost: $55,000 |
- | - | - | - | - | - | $12,636 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$12,636 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $119,408 Cost: $415,764 |
$5,903 | 72,099 | $1,160 | 267 | $13 | - | $12,636 | - | $45,696 | - | $54,000 | - | $5,903 72,099 kWh |
$1,160 267 kW-months/year |
$13 - $ |
$12,636 - $ |
$45,696 - $ |
$54,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $93,329 Cost: $312,539 |
$5,328 | 65,065 | $877 | 202 | $12 | - | $12,636 | - | $20,476 | - | $54,000 | - | $5,328 65,065 kWh |
$877 202 kW-months/year |
$12 - $ |
$12,636 - $ |
$20,476 - $ |
$54,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Administrative Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Electricity Fees | Personnel Changes | Administrative Changes | Primary Raw Material |