IAC Assessment: NV0132
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NV0132
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Nevada
Assessment Year 1999
Principal Product Industrial and Medical Precision Ceramic Products
NAICS n/a
SIC 2951 - Asphalt Paving Mixtures And Blocks
Sales $10,000,000-$50,000,000
# of Employees 95
Plant Area (Sq.Ft.) 82,980
Annual Production 800,000 Pieces
Production Hrs. Annual 4,352
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $170,686 2,069,461 kWh $0.08
Electricity Demand $24,711 5,659 kW-months/year $4.37
Electricity Fees $1,701 - $ -
Natural Gas $67,506 13,003 MMBtu $5.19
TOTAL ENERGY COSTS $270,439
RECOMMENDED SAVINGS* $281,329 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $188,647
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Administrative Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ $ $ MMBtu $ $ $ $
01: 2.3412 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR Savings:
$78,922
Cost:
$210,000
$79,775 979,191 $11,790 2,700 $196 - $(-12,839) (-10,602) - - - - $79,775
979,191
kWh
$11,790
2,700
kW-months/year
$196
-
$
$(-12,839)
(-10,602)
MMBtu
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$15,392
Cost:
$39,424
$12,422 152,403 $2,938 673 $32 - - - - - - - $12,422
152,403
kWh
$2,938
673
kW-months/year
$32
-
$
-
-
MMBtu
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,139
Cost:
$1,760
$1,058 12,896 $78 18 $3 - - - - - - - $1,058
12,896
kWh
$78
18
kW-months/year
$3
-
$
-
-
MMBtu
-
-
$
-
-
$
04: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$4,402
Cost:
$2,405
$(-424) (-6,448) - - - - $4,826 885 - - - - $(-424)
(-6,448)
kWh
-
-
kW-months/year
-
-
$
$4,826
885
MMBtu
-
-
$
-
-
$
05: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$8,219
Cost:
$1,590
- - - - $8,219 - - - - - - - -
-
kWh
-
-
kW-months/year
$8,219
-
$
-
-
MMBtu
-
-
$
-
-
$
06: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$1,012
Cost:
-
- - - - - - - - - - $1,012 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
$1,012
-
$
07: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$172,243
Cost:
$54,000
- - - - - - - - $172,243 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$172,243
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$281,329
Cost:
$309,179
$92,831 1,138,042 $14,806 3,391 $8,450 - $(-8,013) (-9,717) $172,243 - $1,012 - $92,831
1,138,042
kWh
$14,806
3,391
kW-months/year
$8,450
-
$
$(-8,013)
(-9,717)
MMBtu
$172,243
-
$
$1,012
-
$
TOTAL IMPLEMENTED Savings:
$188,647
Cost:
$93,424
$12,422 152,403 $2,938 673 $32 - - - $172,243 - $1,012 - $12,422
152,403
kWh
$2,938
673
kW-months/year
$32
-
$
-
-
MMBtu
$172,243
-
$
$1,012
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Administrative Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Administrative Changes