Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Old Dominion Univ. |
---|---|
Assessment Year | 1997 |
Principal Product | Magazines and books |
NAICS | n/a |
SIC | 2732 - Book Printing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 136,000 |
Annual Production | 71,000,000 Pieces |
Production Hrs. Annual | 7,200 |
Location (State) | MD |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $362,136 | 9,287,222 | kWh | $0.04 |
Electricity Demand | $171,106 | 20,475 | kW-months/year | $8.36 |
Electricity Fees | $345 | - | $ | - |
Natural Gas | $112,078 | 19,552 | MMBtu | $5.73 |
LPG | $114,334 | 17,813 | MMBtu | $6.42 |
TOTAL ENERGY COSTS | $784,163 | |||
RECOMMENDED SAVINGS* | $53,277 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $32,492 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | Water Disposal | Other Liquid (haz) | Electricity Usage | Electricity Demand | LPG | Water Disposal | Other Liquid (haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $12,338 Cost: $25,270 |
$7,998 | 205,158 | - | - | $4,340 | 676 | - | - | - | - |
$7,998 205,158 kWh |
- - kW-months/year |
$4,340 676 MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $818 Cost: $589 |
$818 | 21,102 | - | - | - | - | - | - | - | - |
$818 21,102 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4234 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER |
Savings: $1,617 Cost: $4,378 |
$1,111 | 28,429 | $506 | 61 | - | - | - | - | - | - |
$1,111 28,429 kWh |
$506 61 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,487 Cost: $1,724 |
$1,096 | 28,136 | $391 | 47 | - | - | - | - | - | - |
$1,096 28,136 kWh |
$391 47 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,624 Cost: $1,495 |
- | - | - | - | $1,624 | 253 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,624 253 MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $4,546 Cost: $1,110 |
$3,351 | 85,873 | $1,195 | 143 | - | - | - | - | - | - |
$3,351 85,873 kWh |
$1,195 143 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6124 BURN WASTE OIL FOR HEAT |
Savings: $2,284 Cost: $3,402 |
$(-146) | (-3,810) | $(-57) | (-7) | - | - | - | - | $2,487 | 2,200 |
$(-146) (-3,810) kWh |
$(-57) (-7) kW-months/year |
- - MMBtu |
- - Tgal |
$2,487 2,200 gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $28,563 Cost: $11,432 |
$(-524) | (-13,482) | $(-187) | (-22) | - | - | $29,274 | 9,520,544 | - | - |
$(-524) (-13,482) kWh |
$(-187) (-22) kW-months/year |
- - MMBtu |
$29,274 9,520,544 Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $53,277 Cost: $49,400 |
$13,704 | 351,406 | $1,848 | 222 | $5,964 | 929 | $29,274 | 9,520,544 | $2,487 | 2,200 | $13,704 351,406 kWh |
$1,848 222 kW-months/year |
$5,964 929 MMBtu |
$29,274 9,520,544 Tgal |
$2,487 2,200 gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $32,492 Cost: $15,240 |
$1,390 | 35,756 | $204 | 25 | $1,624 | 253 | $29,274 | 9,520,544 | - | - | $1,390 35,756 kWh |
$204 25 kW-months/year |
$1,624 253 MMBtu |
$29,274 9,520,544 Tgal |
- - gal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | Water Disposal | Other Liquid (haz) | Electricity Usage | Electricity Demand | LPG | Water Disposal | Other Liquid (haz) |