Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Old Dominion Univ. |
---|---|
Assessment Year | 1999 |
Principal Product | Polymer Insulators |
NAICS | n/a |
SIC | 3629 - Electrical Industrial Apparatus, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 135 |
Plant Area (Sq.Ft.) | 110,000 |
Annual Production | 14,000,000 Pieces |
Production Hrs. Annual | 4,076 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $77,819 | 3,652,403 | kWh | $0.02 |
Electricity Demand | $116,244 | 9,840 | kW-months/year | $11.81 |
Electricity Fees | $7,044 | - | $ | - |
TOTAL ENERGY COSTS | $201,107 | |||
RECOMMENDED SAVINGS* | $14,918 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $12,834 Cost: $61,640 |
$4,823 | 225,381 | $8,011 | 664 |
$4,823 225,381 kWh |
$8,011 664 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4113 INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS |
Savings: $447 Cost: $4,020 |
$383 | 17,878 | $64 | 5 |
$383 17,878 kWh |
$64 5 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2611 MODERATE COOLING TOWER OUTLET TEMPERATURE |
Savings: $82 Cost: $20 |
$82 | 3,810 | - | - |
$82 3,810 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,555 Cost: $2,000 |
$1,555 | 72,685 | - | - |
$1,555 72,685 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $14,918 Cost: $67,680 |
$6,843 | 319,754 | $8,075 | 669 | $6,843 319,754 kWh |
$8,075 669 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |