Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Old Dominion Univ. |
---|---|
Assessment Year | 1999 |
Principal Product | Corrugated Steel Deckin |
NAICS | n/a |
SIC | 3316 - Cold Finishing Of Steel Shapes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 32 |
Plant Area (Sq.Ft.) | 10,000 |
Annual Production | 11,650 Tons |
Production Hrs. Annual | 4,335 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $12,334 | 200,469 | kWh | $0.06 |
Electricity Demand | $2,210 | 912 | kW-months/year | $2.42 |
Electricity Fees | $2,554 | - | $ | - |
Natural Gas | $812 | 85 | MMBtu | $9.55 |
TOTAL ENERGY COSTS | $17,910 | |||
RECOMMENDED SAVINGS* | $141,414 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Primary Product | Electricity Usage | Electricity Demand | Personnel Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,532 Cost: $15,691 |
$2,243 | 36,342 | $289 | 119 | - | - | - | - |
$2,243 36,342 kWh |
$289 119 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $87 Cost: $160 |
$87 | 1,465 | - | - | - | - | - | - |
$87 1,465 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $495 Cost: $120 |
$495 | 22,860 | - | - | - | - | - | - |
$495 22,860 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $138,300 Cost: $69,125 |
$(-1,700) | (-19,930) | - | - | $(-80,000) | - | $220,000 | - |
$(-1,700) (-19,930) kWh |
- - kW-months/year |
$(-80,000) - $ |
$220,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $141,414 Cost: $85,096 |
$1,125 | 40,737 | $289 | 119 | $(-80,000) | - | $220,000 | - | $1,125 40,737 kWh |
$289 119 kW-months/year |
$(-80,000) - $ |
$220,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Primary Product | Electricity Usage | Electricity Demand | Personnel Changes | Primary Product |