Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1982 |
Principal Product | BUTTERFLY VALVES |
NAICS | n/a |
SIC | 3494 - Valves And Pipe Fittings, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 70,000 Pieces |
Production Hrs. Annual | 3,400 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $60,700 | 1,465,123 | kWh | $0.04 |
Natural Gas | $45,000 | 15,000 | MMBtu | $3.00 |
TOTAL ENERGY COSTS | $105,700 | |||
RECOMMENDED SAVINGS* | $6,687 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,687 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $707 Cost: $56 |
$707 | 21,102 | - | - |
$707 21,102 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,830 Cost: $400 |
$1,830 | 54,807 | - | - |
$1,830 54,807 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,330 Cost: $1,405 |
$1,330 | 24,033 | - | - |
$1,330 24,033 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,749 Cost: $560 |
- | - | $1,749 | 535 |
- - kWh |
$1,749 535 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $485 Cost: - |
- | - | $485 | 149 |
- - kWh |
$485 149 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3512 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY |
Savings: $586 Cost: - |
$586 | 17,585 | - | - |
$586 17,585 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $6,687 Cost: $2,421 |
$4,453 | 117,527 | $2,234 | 684 | $4,453 117,527 kWh |
$2,234 684 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,687 Cost: $2,421 |
$4,453 | 117,527 | $2,234 | 684 | $4,453 117,527 kWh |
$2,234 684 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |