Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1984 |
Principal Product | REBAR, FENCE POSTS |
NAICS | n/a |
SIC | 3441 - Fabricated Structural Metal |
Sales | $10,000,000-$50,000,000 |
# of Employees | 350 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 200,000 Tons |
Production Hrs. Annual | 4,160 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $6,448,100 | 140,364,891 | kWh | $0.05 |
Natural Gas | $2,154,200 | 637,401 | MMBtu | $3.38 |
TOTAL ENERGY COSTS | $8,602,300 | |||
RECOMMENDED SAVINGS* | $389,222 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $62,850 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,384 Cost: $2,880 |
$1,384 | 41,032 | - | - | - | - |
$1,384 41,032 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,065 Cost: - |
$2,065 | 52,169 | - | - | - | - |
$2,065 52,169 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $557 Cost: $650 |
- | - | $557 | 165 | - | - |
- - kWh |
$557 165 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $58,510 Cost: $174,400 |
$62,460 | 1,580,891 | - | - | $(-3,950) | - |
$62,460 1,580,891 kWh |
- - MMBtu |
$(-3,950) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,956 Cost: $928 |
$2,956 | 76,202 | - | - | - | - |
$2,956 76,202 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3412 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR |
Savings: $323,750 Cost: $847,440 |
$513,750 | 12,168,816 | - | - | $(-190,000) | - |
$513,750 12,168,816 kWh |
- - MMBtu |
$(-190,000) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $389,222 Cost: $1,026,298 |
$582,615 | 13,919,110 | $557 | 165 | $(-193,950) | - | $582,615 13,919,110 kWh |
$557 165 MMBtu |
$(-193,950) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $62,850 Cost: $178,208 |
$66,800 | 1,698,125 | - | - | $(-3,950) | - | $66,800 1,698,125 kWh |
- - MMBtu |
$(-3,950) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |