IAC Assessment: OK0245
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0245
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 1988
Principal Product STEEL FABRICATION
NAICS n/a
SIC 3441 - Fabricated Structural Metal
Sales $10,000,000-$50,000,000
# of Employees 55
Plant Area (Sq.Ft.) 0
Annual Production 35 Pieces
Production Hrs. Annual 4,300
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $60,923 808,910 kWh $0.08
Natural Gas $6,899 1,581 MMBtu $4.36
TOTAL ENERGY COSTS $67,822
RECOMMENDED SAVINGS* $5,468 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,478
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,990
Cost:
$1,597
$2,185 33,705 - - $(-195) - $2,185
33,705
kWh
-
-
MMBtu
$(-195)
-
$
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,224
Cost:
$1,710
- - $1,224 281 - - -
-
kWh
$1,224
281
MMBtu
-
-
$
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,523
Cost:
$645
- - $1,523 394 - - -
-
kWh
$1,523
394
MMBtu
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$651
Cost:
-
$741 11,430 - - $(-90) - $741
11,430
kWh
-
-
MMBtu
$(-90)
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$80
Cost:
$64
$80 1,172 - - - - $80
1,172
kWh
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$5,468
Cost:
$4,016
$3,006 46,307 $2,747 675 $(-285) - $3,006
46,307
kWh
$2,747
675
MMBtu
$(-285)
-
$
TOTAL IMPLEMENTED Savings:
$3,478
Cost:
$2,419
$821 12,602 $2,747 675 $(-90) - $821
12,602
kWh
$2,747
675
MMBtu
$(-90)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes