IAC Assessment: OK0284
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0284
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 1989
Principal Product FABRICATED STEEL
NAICS n/a
SIC 3441 - Fabricated Structural Metal
Sales $10,000,000-$50,000,000
# of Employees 260
Plant Area (Sq.Ft.) 0
Annual Production 400,000 Pieces
Production Hrs. Annual 4,160
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $164,893 3,378,077 kWh $0.05
Natural Gas $28,986 9,765 MMBtu $2.97
TOTAL ENERGY COSTS $193,879
RECOMMENDED SAVINGS* $56,255 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $56,255
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$738
Cost:
$1,250
- - $738 246 - - -
-
kWh
$738
246
MMBtu
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$34,480
Cost:
$36,560
$34,462 703,107 - - $18 - $34,462
703,107
kWh
-
-
MMBtu
$18
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,250
Cost:
$3,808
$1,366 27,843 - - $(-116) - $1,366
27,843
kWh
-
-
MMBtu
$(-116)
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$400
Cost:
$825
$400 6,741 - - - - $400
6,741
kWh
-
-
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$289
Cost:
$275
$289 4,982 - - - - $289
4,982
kWh
-
-
MMBtu
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$560
Cost:
$3,432
$632 15,826 - - $(-72) - $632
15,826
kWh
-
-
MMBtu
$(-72)
-
$
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$10,197
Cost:
$31,028
$10,197 318,581 - - - - $10,197
318,581
kWh
-
-
MMBtu
-
-
$
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$6,816
Cost:
$2,140
- - $6,816 2,272 - - -
-
kWh
$6,816
2,272
MMBtu
-
-
$
09: 2.3513 CONSIDER POWER LOSS AS WELL AS INITIAL LOADS AND LOAD GROWTH IN DOWN-SIZING TRANSFORMERS Savings:
$1,525
Cost:
-
$1,745 54,513 - - $(-220) - $1,745
54,513
kWh
-
-
MMBtu
$(-220)
-
$
TOTAL RECOMMENDED Savings:
$56,255
Cost:
$79,318
$49,091 1,131,593 $7,554 2,518 $(-390) - $49,091
1,131,593
kWh
$7,554
2,518
MMBtu
$(-390)
-
$
TOTAL IMPLEMENTED Savings:
$56,255
Cost:
$79,318
$49,091 1,131,593 $7,554 2,518 $(-390) - $49,091
1,131,593
kWh
$7,554
2,518
MMBtu
$(-390)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes