Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1990 |
Principal Product | AMUSEMENT RIDE EQUIPMENT |
NAICS | n/a |
SIC | 3599 - Industrial Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 350 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 132 Pieces |
Production Hrs. Annual | 5,200 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $220,424 | 2,751,172 | kWh | $0.08 |
Natural Gas | $73,002 | 23,625 | MMBtu | $3.09 |
TOTAL ENERGY COSTS | $293,426 | |||
RECOMMENDED SAVINGS* | $14,481 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,256 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,239 Cost: $2,150 |
$1,538 | 21,395 | $1,701 | 551 | - | - |
$1,538 21,395 kWh |
$1,701 551 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $2,549 Cost: $750 |
- | - | $2,549 | 825 | - | - |
- - kWh |
$2,549 825 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,942 Cost: $1,641 |
- | - | $2,942 | 952 | - | - |
- - kWh |
$2,942 952 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $578 Cost: $190 |
$578 | 8,206 | - | - | - | - |
$578 8,206 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,396 Cost: - |
$2,546 | 35,463 | - | - | $(-150) | - |
$2,546 35,463 kWh |
- - MMBtu |
$(-150) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,283 Cost: $632 |
$1,283 | 14,361 | - | - | - | - |
$1,283 14,361 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,494 Cost: $975 |
$1,525 | 16,999 | - | - | $(-31) | - |
$1,525 16,999 kWh |
- - MMBtu |
$(-31) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $14,481 Cost: $6,338 |
$7,470 | 96,424 | $7,192 | 2,328 | $(-181) | - | $7,470 96,424 kWh |
$7,192 2,328 MMBtu |
$(-181) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,256 Cost: $4,065 |
$6,187 | 82,063 | $4,250 | 1,376 | $(-181) | - | $6,187 82,063 kWh |
$4,250 1,376 MMBtu |
$(-181) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |