Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1991 |
Principal Product | FLOOR CLEANING EQUIPMENT |
NAICS | n/a |
SIC | 3589 - Service Industry Machinery, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 213 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 10,500 Pieces |
Production Hrs. Annual | 2,250 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $137,151 | 2,560,082 | kWh | $0.05 |
Natural Gas | $66,242 | 16,325 | MMBtu | $4.06 |
TOTAL ENERGY COSTS | $203,393 | |||
RECOMMENDED SAVINGS* | $11,115 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,115 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $9,744 Cost: $3,000 |
- | - | $9,744 | 2,400 | - | - |
- - kWh |
$9,744 2,400 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $563 Cost: $549 |
$563 | 10,258 | - | - | - | - |
$563 10,258 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $808 Cost: - |
$908 | 32,239 | - | - | $(-100) | - |
$908 32,239 kWh |
- - MMBtu |
$(-100) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,115 Cost: $3,549 |
$1,471 | 42,497 | $9,744 | 2,400 | $(-100) | - | $1,471 42,497 kWh |
$9,744 2,400 MMBtu |
$(-100) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,115 Cost: $3,549 |
$1,471 | 42,497 | $9,744 | 2,400 | $(-100) | - | $1,471 42,497 kWh |
$9,744 2,400 MMBtu |
$(-100) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |