IAC Assessment: OK0516
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0516
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 1997
Principal Product surgical cameras
NAICS n/a
SIC 3842 - Surgical Appliances And Supplies
Sales $10,000,000-$50,000,000
# of Employees 0
Plant Area (Sq.Ft.) 60,000
Annual Production 14,400 Pieces
Production Hrs. Annual 2,470
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $23,196 791,618 kWh $0.03
Electricity Demand $24,514 2,182 kW-months/year $11.23
Electricity Fees $876 - $ -
Natural Gas $4,807 846 MMBtu $5.68
TOTAL ENERGY COSTS $53,393
RECOMMENDED SAVINGS* $8,291 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,788
#|Description Savings
Cost
Status Electricity Usage Natural Gas Solid Waste (non-haz) Personnel Changes Electricity Usage Natural Gas Solid Waste (non-haz) Personnel Changes
$ kWh $ MMBtu $ lb $ $
01: 2.6232 INSTALL SET-BACK TIMERS Savings:
$2,215
Cost:
$3,472
- - $2,215 390 - - - - -
-
kWh
$2,215
390
MMBtu
-
-
lb
-
-
$
02: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$5,088
Cost:
-
- - - - $5,088 - - - -
-
kWh
-
-
MMBtu
$5,088
-
lb
-
-
$
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$415
Cost:
$1,056
$415 5,275 - - - - - - $415
5,275
kWh
-
-
MMBtu
-
-
lb
-
-
$
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$304
Cost:
$542
$451 6,741 $(-147) (-26) - - - - $451
6,741
kWh
$(-147)
(-26)
MMBtu
-
-
lb
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$269
Cost:
$395
$129 2,931 - - - - $140 - $129
2,931
kWh
-
-
MMBtu
-
-
lb
$140
-
$
TOTAL RECOMMENDED Savings:
$8,291
Cost:
$5,465
$995 14,947 $2,068 364 $5,088 - $140 - $995
14,947
kWh
$2,068
364
MMBtu
$5,088
-
lb
$140
-
$
TOTAL IMPLEMENTED Savings:
$2,788
Cost:
$4,409
$580 9,672 $2,068 364 - - $140 - $580
9,672
kWh
$2,068
364
MMBtu
-
-
lb
$140
-
$
Savings
Cost
$ kWh $ MMBtu $ lb $ $
Electricity Usage Natural Gas Solid Waste (non-haz) Personnel Changes Electricity Usage Natural Gas Solid Waste (non-haz) Personnel Changes