Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1997 |
Principal Product | Cut up poultry |
NAICS | n/a |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $50,000,000-$100,000,000 |
# of Employees | 1,100 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 265,000,000 Pounds |
Production Hrs. Annual | 8,520 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $725,521 | 28,991,794 | kWh | $0.03 |
Electricity Demand | $200,187 | 24,360 | kW-months/year | $8.22 |
Natural Gas | $279,016 | 92,263 | MMBtu | $3.02 |
TOTAL ENERGY COSTS | $(-1,800,450) | |||
RECOMMENDED SAVINGS* | $70,561 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,289 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,774 Cost: $17,415 |
$2,567 | 102,579 | $1,294 | 321 | - | - | - | - | $(-87) | - |
$2,567 102,579 kWh |
$1,294 321 kW-months/year |
- - MMBtu |
- - Tgal |
$(-87) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1231 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS |
Savings: $7,965 Cost: $5,000 |
- | - | - | - | $7,965 | 2,634 | - | - | - | - |
- - kWh |
- - kW-months/year |
$7,965 2,634 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $6,577 Cost: $8,566 |
- | - | - | - | $6,577 | 2,175 | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,577 2,175 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS |
Savings: $3,330 Cost: - |
- | - | - | - | - | - | - | - | $3,330 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$3,330 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4151 MINIMIZE WATER USAGE |
Savings: $47,695 Cost: $7,520 |
- | - | - | - | - | - | $47,695 | 51,120,000 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$47,695 51,120,000 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,220 Cost: $2,561 |
$2,194 | 87,632 | - | - | $(-974) | (-322) | - | - | - | - |
$2,194 87,632 kWh |
- - kW-months/year |
$(-974) (-322) MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $70,561 Cost: $41,062 |
$4,761 | 190,211 | $1,294 | 321 | $13,568 | 4,487 | $47,695 | 51,120,000 | $3,243 | - | $4,761 190,211 kWh |
$1,294 321 kW-months/year |
$13,568 4,487 MMBtu |
$47,695 51,120,000 Tgal |
$3,243 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,289 Cost: $24,976 |
$4,761 | 190,211 | $1,294 | 321 | $6,991 | 2,312 | - | - | $3,243 | - | $4,761 190,211 kWh |
$1,294 321 kW-months/year |
$6,991 2,312 MMBtu |
- - Tgal |
$3,243 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes |